Oregon Natural Desert Association v. Bureau of Land Management

Oregon Natural Desert Association and two other environmental groups[1] (collectively ONDA) appealed a grant of summary judgment by the District Court for the District of Oregon in favor of the defendant, the Bureau of Land Management (BLM) regarding the BLM’s Southeast Oregon Resource Management Plan (Plan) and corresponding environmental impact statement (EIS) for a large portion of southeastern Oregon. The Ninth Circuit reversed and remanded, holding that BLM violated the National Environmental Policy Act (NEPA)[2] by failing to address concerns about wilderness characteristics and failing to consider alternatives that would have closed more acreage to off-road vehicles (ORVs). The Ninth Circuit set aside BLM’s record of decision (ROD) approving the EIS and the corresponding land use plan and remanded the case with instructions to BLM to remedy the NEPA deficiencies.

BLM began developing a comprehensive management plan for approximately 4.5 million acres of land in southeastern Oregon in 1995. The area is characterized by a semi-arid climate and rugged, scenic landscape that supports sagebrush plains and juniper woodlands. Economic indicators place the region’s economy, largely dependent on farming and ranching, far below statewide averages. Because federally owned land comprises a large portion of the area, BLM management of its share has a significant effect on the region’s natural resources and economy.

BLM land management authority is defined by the Federal Land Policy and Management Act (FLPMA).[3] FLPMA requires BLM to develop, maintain, and revise land-use plans using a systematic interdisciplinary management approach that gives priority to the designation and protection of areas of critical environmental concern and weighs short- and long-term benefits to the public.[4] An extensive public comment process is integral to the formulation of BLM plans.[5] Any party that has participated in the planning process and may be adversely affected may protest the approval of a BLM land-use plan.[6]

FLPMA interacts with the Wilderness Act[7] to provide BLM with broad authority to manage areas with wilderness characteristics on public lands. Specifically, FLPMA provides BLM with a process to protect areas with wilderness characteristics from impairment by designating them as Wilderness Study Areas (WSA) and recommending them for congressional protection.[8] FLPMA also authorizes BLM to account for wilderness characteristics as part of its inventory of public lands, their resources, and other values.[9]

The approval of a resource management plan by a ROD implicates NEPA[10] and requires the preparation of an EIS.[11] In contrast to the substantive rights and obligations created by land management statutes such as FLPMA, NEPA puts in place procedures to ensure that decision makers consider information about environmental impacts and disseminate such findings for public participation. An EIS guides decision making by requiring the agency to consider all significant aspects of environmental impacts[12] and list reasonable alternatives.[13]

In the case at bar, after three years of planning, BLM released a draft management plan (Plan) and corresponding draft EIS as one document created to guide management of southeastern Oregon for the next twenty years. ONDA’s comments on the draft EIS criticized BLM for failing to inventory lands that had developed wilderness characteristics since BLM’s prior survey of those values in 1980.[14] ONDA also contended that BLM did not consider a reasonable range of alternatives, arguing that the agency failed to account for the cumulative impacts of grazing and the excessive quantity of land left open to ORV use.

After reviewing comments on the draft EIS, BLM released its final version of the Plan and EIS in 2001. In response to ONDA’s comments, BLM noted that it had already taken a wilderness inventory pursuant to 43 U.S.C. § 1782(b)[15] and expressly disclaimed an obligation to analyze the effects of its Plan on wilderness values or consider management options for areas with those characteristics.[16] BLM considered conferring additional protections from development and disruptive uses to several hundred thousand acres of land in areas of critical environmental concern,[17] but such designations were limited and did not imply the presence of wilderness characteristics, much less protect them.

BLM selected the Plan from among seven draft alternatives. With regard to ORV use, the alternatives varied almost entirely by the amount of land allocated between open and limited-use categories. [18] Most notably, BLM never considered closing a significant amount of land to ORVs, nor did it consider an option geared toward protecting wilderness values from ORV use. The most protective limited-use category restricted ORVs to existing routes in WSAs and other sensitive areas and imposed seasonal closures to protect wildlife, but these limitations would still have allowed ORVs to travel up to 150 feet off an existing road in certain circumstances.[19] Every alternative exposed more land to some type of ORV use than was previously permitted. For example, the Plan’s selected alternative opened approximately 20,000 acres of previously closed land to some ORV use.[20] With regard to grazing, only one alternative deemed valid by BLM contemplated substantial restrictions, and BLM did not consider limiting grazing in areas with wilderness characteristics outside of WSAs.

ONDA filed a protest with BLM in December 2001, sounding the same concerns it raised in its comments to the draft EIS. ONDA alleged that BLM’s failure to provide information about and analyze wilderness values “violated NEPA’s requirement that the [BLM] engage in fully-informed decisionmaking.”[21] ONDA also challenged the limited alternatives for grazing management, emphasizing that BLM did not consider cumulative impacts. Finally, ONDA raised concerns that none of the Plan’s alternatives closed more than 0.8% of the planning area to ORV use. BLM denied the protest in September 2002, explaining that its wilderness review duty under the Wilderness Act was a “one-time responsibility” that was fulfilled by its 1991 report.[22] With regard to grazing, BLM responded that the alternatives were adequate because each had different effects over the short- and long-term. With regard to ORV use, BLM stated that its alternatives were adequate because the “limited” designation provided comparable protection to the “closed” designation. BLM adopted the Plan in an April 2003 ROD.

In response, ONDA filed suit against BLM in July 2003. In the meantime, ONDA undertook a survey of the Plan area to document changes that had occurred since 1980. ONDA submitted the results to BLM in February 2004 and introduced it as evidence in the pending suit. The district court expanded its review beyond the April 2003 ROD by admitting the survey because of precedent permitting new evidence “where the plaintiff alleges that an EIS has . . . swept stubborn problems or serious criticism under the rug.”[23] The survey demonstrated how the planning area, especially portions with unmaintained roads, had changed over time, with some reductions in human impacts. Despite the survey’s conclusion that the planning area had changed significantly and the existence of specific data showing more than 1.3 million acres of land outside of WSAs that display wilderness characteristics,[24] BLM did not modify the Plan or take new action.[25]

In its suit, ONDA alleged violations of NEPA, FLPMA, and the Taylor Grazing Act.[26] Both parties moved for summary judgment, and the district court, adopting the magistrate judge’s findings and recommendations, awarded summary judgment to BLM. ONDA timely appealed, and the Ninth Circuit reviewed the district court’s ruling de novo.[27] The Ninth Circuit reviewed BLM’s Plan and EIS under the Administrative Procedure Act (APA)[28] “arbitrary and capricious” standard. Although ONDA also appealed the district court’s rulings on its FLPMA and Taylor Grazing Act claims, the Ninth Circuit limited its opinion to ONDA’s NEPA claims.

The Ninth Circuit began its analysis of whether BLM violated NEPA by failing to inventory and discuss wilderness characteristics in the EIS. NEPA applies broadly to a variety of federal actions that impact the environment and does not contain requirements about substantive elements such as wilderness characteristics. These requirements are derived from the substantive statute compelling the proposed action. In this case, approval of the resource management plan constitutes a federal action and is compelled by FLPMA. ONDA argued that BLM, by declining to analyze wilderness characteristics on non-WSA lands, failed to adequately discuss the Plan’s impacts and alternatives despite ONDA’s comments. BLM responded that wilderness characteristics are only relevant to a one-time duty to survey wilderness areas under 43 U.S.C. § 1782. BLM’s argument was consistent with its position in Utah v. Norton,[29] where it agreed to, among other things, cease establishing, managing, or treating public lands as WSAs or as wilderness without congressional authorization.[30] Although the Utah settlement’s validity depended upon BLM’s compliance with FLPMA and NEPA, BLM and ONDA shared the position that the court need not directly consider the settlement’s legality.

After considering these arguments, the Ninth Circuit held that BLM’s response to ONDA’s concerns failed to satisfy NEPA requirements. The court cited 43 U.S.C. §§ 1712 and 1732 for BLM’s authority, independent of the one-time duty to survey lands with wilderness characteristics under 43 U.S.C. § 1782, to manage resources such as wilderness values. In essence, the court explained “wilderness characteristics retain vitality as a resource category covered by the BLM’s multiple-use land use planning mandate” even where section 1782 review has been completed.[31] The court explained this conclusion by examining 1) the statutory and regulatory structure binding BLM, 2) BLM’s guidance documents and public statements, and 3) case law.

The Ninth Circuit’s contextual interpretation of FLPMA, the Wilderness Act, and corresponding regulations supported the conclusion that BLM is required to address wilderness values in a detailed NEPA analysis. For example, FLPMA and corresponding regulations establish “wilderness characteristics” by referencing the Wilderness Act, and the definition of “wilderness” is the same in both statutes. The court cited BLM’s land-use planning handbook and the BLM’s administrative adjudicative body for recognizing that the characterizations of “wilderness” in FLPMA are identical to those in the Wilderness Act. Based on these cross-referencing definitions, the court concluded the wilderness characteristics concept originates from the statutory framework.

The Ninth Circuit explained that FLPMA’s Wilderness Study provision, which directs BLM to conduct an initial wilderness review to make recommendations for wilderness preservation, does not limit wilderness inventories to the recommendation process.[32] Instead, the Wilderness Study provision references 43 U.S.C. § 1711(a), which provides for a continuous inventory process to reflect new resources and other values.[33] Read together, section 1711(a) and section 1782(a) presume that BLM’s inventory procedure will identify areas with wilderness characteristics, including “new and emerging” areas or those arising from a “change in conditions.”[34] It also follows that wilderness characteristics are equivalent to “resource and other values” recognized under section 1711(a). Thus, the Ninth Circuit reasoned that BLM must manage wilderness characteristics as one aspect of its broad authority under its multiple-use management and planning mandate.

After recognizing BLM’s duty under FLPMA to consider wilderness characteristics, the court outlined several management methods that BLM could employ to fulfill its responsibilities of managing lands for wilderness values as part of multiple-use management. These suggestions included 1) enacting limitations on extractive uses, 2) reducing levels of potentially destructive grazing or ORV uses, 3) designating lands as areas of critical environmental concern or research natural areas, and 4) implementing a temporary nonimpairment policy. The court recognized that as long as BLM gave adequate consideration to wilderness characteristics during the planning process, it could implement a management plan that did not aspire to long-term wilderness preservation.

BLM’s public guidance documents supported the Ninth Circuit’s understanding that FLPMA instructs BLM to manage wilderness values of lands and corresponding duties to discuss such resources in NEPA documentation. The BLM’s 2005 Land Use Planning Handbook (2005 Handbook) acknowledged a continuing authority to manage lands with wilderness characteristics in land-use plans.[35] The 2005 Handbook also
recognized a duty to include analysis of wilderness characteristics, as appropriate, in EIS documentation.[36]

The Ninth Circuit also cited case law in support of its conclusion that BLM should have considered wilderness characteristics, particularly the roadless character of such lands, in its NEPA analysis. The court premised that roadlessness and wilderness were nearly inseparable considerations, because roadlessness is essential to fulfilling the “natural conditions” component of “wilderness” as defined in the Wilderness Act.[37] Then, the court compared circuit cases discussing roadlessness. In Smith v. United States Forest Service,[38] the Ninth Circuit rejected the Forest Service’s argument, analogous to that made by BLM, that it lacked a duty to discuss roadlessness in its NEPA documents, and held that roadlessness has an environmental significance that must be analyzed in NEPA documents.[39] In 2007, the Ninth Circuit applied Smith’s holding to noninventoried areas greater than 5000 acres and inventoried areas smaller than 5000 acres.[40] The court reasoned that if roadlessness, a significant feature of wilderness, merited NEPA consideration on Forest Service land, wilderness characteristics on BLM land similarly warranted NEPA documentation.

BLM advanced three counter-arguments that failed to persuade the Ninth Circuit. First, BLM argued that the United States Supreme Court’s holding in Norton v. Southern Utah Wilderness Alliance (SUWA)[41] limiting suits under the APA barred review of BLM’s failure to consider wilderness characteristics. Second, BLM argued that a ruling for ONDA about wilderness characteristics would violate the Supreme Court’s holding in Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council (Vermont Yankee).[42] Third, BLM argued that its analysis of other resources incidentally benefited wilderness values, and that the Ninth Circuit should defer to its NEPA methodology.

The Ninth Circuit disregarded BLM’s argument that SUWA applied to ONDA’s challenge because the case arose from a different provision of the APA. SUWA held that under section 706(1) of the APA a plaintiff must assert that an agency failed to take a discrete, required action.[43] BLM argued that a duty to inventory wilderness characteristics was not discrete. However, ONDA’s claim arose under section 706(2)(A), challenging BLM’s actions as “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” The court referenced more than a dozen cases for the proposition that the process of finalizing an EIS as a ROD constituted a final agency action, subject to review under section 706(2)(A). Thus, the court reviewed “the validity of the final action that was taken, not-as in SUWA-demanding that the agency take some action that it has not taken.”[44] The court explained that a contrary holding would make it difficult for a plaintiff to challenge an agency’s analytic errors under NEPA, because there is often no discrete duty required by statute to consider a specific issue. Under arbitrary and capricious review, an agency must consider nondiscrete issues of environmental significance before committing to a major federal action.

The Ninth Circuit rejected BLM’s argument that Vermont Yankee applied to ONDA’s challenge. In Vermont Yankee, the Supreme Court held that courts cannot use NEPA to substantially revise an agency’s procedural obligations under the APA or impose the court’s notion of which procedures are superior.[45] The Ninth Circuit reasoned that its holding required only direct compliance with NEPA’s EIS requirement and did not create any extra procedural requirements. In rejecting the relevance of Vermont Yankee, the Ninth Circuit emphasized that BLM, on remand, could decide how to fulfill its NEPA obligations regarding consideration of wilderness characteristics.

The Ninth Circuit also rejected BLM’s argument that its NEPA analysis of other resources incidentally contemplated the Plan’s effects on wilderness characteristics. The court viewed this argument as an unacceptable “post hoc rationalization”[46] because BLM did not articulate this position in the EIS. The Ninth Circuit also criticized the premise of BLM’s argument, which depicted wilderness characteristics as a “nebulous term.”[47] The court warned that developing a “proxy methodology” may fail to provide adequate disclosure of wilderness values present on BLM land.[48] Finally, because BLM lacked a method of analyzing or managing wilderness values, the court reasoned that it owed no deference to the BLM methodology, stating “[w]e cannot defer to a void.”[49]

Basing its conclusions on the statutes, regulations, guidance documents, and case law, the Ninth Circuit ruled against BLM on the wilderness values issue. The court held that 1) BLM had continuing authority to manage wilderness characteristics under FLPMA, wholly distinct from the agency’s duty to survey the land for wilderness preservation recommendations, 2) BLM violated NEPA by failing to properly respond to ONDA’s comments and provide a “full and fair discussion” about wilderness values in the EIS, and 3) BLM violated NEPA by failing to consider cumulative impacts on the planning area, because it did not consider impacts on lands with wilderness characteristics.

Next, the Ninth Circuit addressed ONDA’s other NEPA arguments pertaining to BLM’s alternatives analyses for grazing and ORV management. Citing Westlands Water District v. Department of Interior,[50] the court reasoned that “[t]he existence of a viable but unexamined alternative renders an environmental impact statement inadequate.”[51] With regard to both issues, the Ninth Circuit reasoned that BLM’s analysis of wilderness values on remand could lead to more adequate alternatives, but the court specifically held that BLM should consider an alternative that closed significant portions of land.

The Ninth Circuit did not decide whether BLM’s grazing alternatives were deficient. ONDA argued that BLM’s consideration of only one option that reduced grazing area and intensity amounted to a failure to adequately explore the balance between development and wilderness use.[52] The court reasoned that BLM, in its consideration of lands with wilderness values, would have the opportunity to “address the bias towards grazing” and produce more adequate alternatives.[53]

The Ninth Circuit ruled that BLM’s ORV use alternatives failed to provide the agency or public with a proper consideration of options. First, wilderness characteristics did not factor into BLM’s analysis of its ORV designations. Second, the court observed that no ORV alternative proposed closing more than a fraction of the planning area to ORVs and each alternative reduced the amount of areas that were previously closed to such use. The court disagreed with BLM’s argument that a wide range of open and limited ORV designations paired with emergency closure provisions was adequate, bluntly stating that limited use is “not identical” to no use.[54] The court specifically criticized the limitation to existing routes designation that permitted ORV use up to 150 feet off trails. Finally, the Ninth Circuit concluded that BLM must consider closing significant portions of land, especially those with wilderness characteristics.

In conclusion, the Ninth Circuit held that the EIS was invalid under NEPA because it did not address concerns about wilderness characteristics and also lacked alternatives that closed significant portions of the planning area to ORV use. The Ninth Circuit set aside BLM’s ROD approving the Plan and accompanying EIS and remanded the case to the district court with instructions for further remand to the BLM.


[1] Committee for the High Desert and Western Watersheds Project joined in the suit but did not join ONDA in commenting on BLM’s draft environmental impact statement.

[2] National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4370e (2006).

[3] Federal Land Policy and Management Act of 1976, 43 U.S.C. §§ 1701-1785 (2006).

[4] Id. § 1712(c).

[5] 43 C.F.R. § 1610.2 (2007).

[6] Id. § 1610.5-2(a).

[7] 16 U.S.C. §§ 1131-1136 (2006).

[8] 43 U.S.C. § 1782(b) (2006).

[9] Id. § 1711.

[10] 43 C.F.R. § 1601.0-6 (2007).

[11] 42 U.S.C. § 4332(C) (2006).

[12] Pit River Tribe v. U.S. Forest Serv., 469 F.3d 768, 781 (9th Cir. 2006); see also 40 C.F.R. pt. 1502 (2007).

[13] 40 C.F.R. § 1502.14 (2007).

[14] After identifying 32 WSAs in the planning area and completing a final EIS, BLM submitted its recommendations to the President, advising permanent preservation for 21 WSAs, and in 1992, the President submitted these recommendations to Congress. Congress has not acted on these recommendations.

[15] 3 Bureau of Land Mgmt., U.S. Dep’t of the Interior, Proposed Southeastern Oregon Resource Management Plan and Final Environmental Statement 105 (2001), available at http://www.blm.gov/or/districts/vale/plans/files/seormp/SEORMP%20Final%20Volume%203%
20Text.pdf [hereinafter FEIS].

[16] The Plan did consider two management possibilities for approximately 3000 acres of land adjacent to WSAs created pursuant to its recommendations to Congress. 1 FEIS, supra note 443, at 373-75.

[17] Id. at 276-368; see also Federal Land Policy and Management Act of 1976, 43 U.S.C. § 1712(c)(3) (2006).

[18] 1 FEIS, supra note 15, at xxii, 269-73.

[19] Id. at 273.

[20] Id. at xxii, 269-73.

[21] Or. Natural Desert Ass’n v. BLM (ONDA), 531 F.3d 1114, 1127 (9th Cir. 2008).

[22] Id. at 1127.

[23] Or. Natural Res. Council v. Lowe, 109 F.3d 521, 526-27 (9th Cir. 1997).

[24] Or. Natural Desert Ass’n, Wilderness Inventory Recommendations: Vale District (2004).

[25] BLM did not appeal the admission of ONDA’s survey. The Ninth Circuit described the survey “without expressly approving or disapproving of its particular findings” but rather “to demonstrate how the presence of wilderness values may change over time and how wilderness characteristics may have been reestablished in parts of the area covered by the Southeast Oregon Plan.” ONDA, 531 F.3d at 1128.

[26] Federal Land Policy and Management Act of 1976, 43 U.S.C. §§ 315-315o-1 (2006).

[27] Klamath-Siskiyou Wildlands Ctr. v. BLM, 387 F.3d 989, 992 (9th Cir. 2004).

[28] 5 U.S.C. §§ 551-559, 701-706, 1305, 3105, 3344, 4301, 5335, 5362, 7521 (2006). The arbitrary and capricious standard is at section 706(2)(A).

[29] No. 2:96-CV-0870, 2006 WL 2711798 (D. Utah Sept. 20, 2006); see also Utah v. Norton, 396 F.3d 1281, 1284-85 (10th Cir. 2005).

[30] Norton, 2006 WL 2711798, at *4.

[31] ONDA, 531 F.3d 1114, 1136 (9th Cir. 2008).

[32] Federal Land Policy and Management Act of 1976, 43 U.S.C. § 1782(a) (2006).Note that section 1782(a) references section 1711(a)’s required inventory, but does not direct that areas with wilderness characteristics be identified only as part of recommending such areas for “preservation as wilderness.”

[33] Id. § 1711(a).

[34] ONDA, 531 F.3d at 1134.

[35] Bureau of Land Mgmt., U.S. Dep’t of the Interior, Land Use Planning Handbook app. C, at 1, 12 (2005) [hereinafter 2005 Handbook]; see also id. app. F, at 7.

[36] See id. app. F, at 16. Noting a discrepancy between BLM’s appellate briefs and the agency’s guidance documents, the court relied on the latter, reasoning that the guidance documents were well-reasoned, persuasive, and consistent with the Ninth Circuit’s interpretation of the statutes in question.

[37] Wukderbess Act, 16 U.S.C. § 1131(c) (2006).

[38] 33 F.3d 1072 (9th Cir. 1994).

[39] Id. at 1078.

[40] Lands Council v. Martin, 479 F.3d 636, 640 (9th Cir. 2007).

[41] 542 U.S. 55 (2004).

[42] 435 U.S. 519 (1978).

[43] SUWA, 542 U.S. at 64.

[44] ONDA, 531 F.3d. 1

Northwest Environmental Advocates v. U.S. Environmental Protection Agency

Northwest Environmental Advocates, the Ocean Conservancy, and San Francisco Baykeeper (collectively NWEA) brought suit in federal district court against the United States Environmental Protection Agency (EPA), alleging that a regulation exempting certain marine discharges from the permitting scheme of sections 301(a) and 402 of the Clean Water Act (CWA)[1] was beyond the scope of the Act. The district court concluded EPA exceeded its authority under the CWA in exempting the marine discharges from the permitting requirements and vacated challenged portions of the regulation. On appeal, the Ninth Circuit affirmed the decision of the district court and held that EPA’s regulation was invalid as an ultra vires act unauthorized by the CWA.

Section 301 of the CWA provides that, subject to certain exceptions, the discharge of any pollutant by any person is unlawful.[2] One exception to section 301 applies to discharges authorized by a permit granted pursuant to the National Pollutant Discharge Elimination System (NPDES), which is set forth in section 402 of the CWA.[3] The combined effect of sections 301(a) and 402 is that the “CWA prohibits the discharge of any pollutant from a point source into navigable waters of the United States without an NPDES permit.”[4]

In 1973, EPA promulgated a regulation exempting several categories of vessel discharges from NPDES permitting requirements.[5] The regulation, 40 C.F.R. § 122.3(a), exempts “any discharge of sewage from vessels, effluent from properly functioning marine engines, laundry, shower, and galley sink wastes from vessels, or any other discharge incidental to the normal operation of a vessel” from the permitting requirements of the NPDES program.[6] The CWA expressly exempts the discharge of vessel sewage from the NPDES permitting process and regulates such discharges by other means. As such, only three categories of discharges exempted by 40 C.F.R. § 122.3(a) were at issue in NWEA’s ultra vires claim: 1) marine engine discharges, 2) gray water discharges such as laundry, shower, and galley sink wastes, and 3) any other discharge incidental to the normal operation of a vessel, including ballast water.

NWEA’s primary concern with the regulation stemmed from the ballast water exemption. Ballast water is taken in by vessels and used for a number of purposes, including maintaining stability and compensating for changes in a ship’s cargo weights. Because ballast water is used primarily to compensate for changes in cargo, it is generally taken in and pumped out at ports along a ship’s route. In the process of gaining or releasing ballast water, ships also redistribute the living organisms present in the water. Many of these foreign organisms survive the journey to a new ecosystem and reproduce; these invasive species often have severe impacts on humans, the environment, and the economy.

NWEA had petitioned EPA for repeal of 40 C.F.R. § 122.3(a). After EPA denied NWEA’s petition, NWEA brought suit against EPA in federal district court, alleging that 40 C.F.R. § 122.3(a) is not authorized by the CWA and is therefore ultra vires.[7] NWEA’s second cause of action claimed, based on the ultra vires argument, that EPA’s rejection of its petition was “not in accordance with the law.”[8] To preserve subject matter jurisdiction, at the same time as NWEA filed suit in the district court, NWEA also filed a petition for review of EPA’s decision in the Ninth Circuit Court of Appeals.

The district court granted summary judgment in favor of NWEA on the first cause of action and ordered EPA to repeal 40 C.F.R. § 122.3(a). Additionally, the district court ordered further proceedings to determine the appropriate remedy.[9] EPA and defendant-intervenor Shipping Industry Ballast Water Coalition appealed the district court’s decision to vacate the challenged portions of the regulation and the Ninth Circuit consolidated the appeal with the petition filed directly by NWEA in the Ninth Circuit.

The Ninth Circuit reviews de novo questions involving subject matter jurisdiction,[10] application of a statute of limitations,[11] a district court’s grant of summary judgment,[12] and exhaustion of necessary administrative remedies.[13] Issues regarding whether a regulation exceeds the scope of a statute are reviewed by the Ninth Circuit under the Administrative Procedure Act,[14] which requires the court to set aside agency actions that exceed the jurisdiction, authority, or limitations of a statute.[15]

On appeal, EPA argued that the district court lacked subject matter jurisdiction over NWEA’s suit and that the Ninth Circuit should order the district court to dismiss the case. In the alternative, assuming the district court had subject matter jurisdiction, EPA claimed the statute of limitations barred NWEA’s ultra vires claim, the district court erred in finding that the CWA did not authorize the regulatory exemptions, and the district court abused its discretion in selecting the remedy.

In reviewing the district court’s decision, the Ninth Circuit first turned to the threshold question of whether the district court had subject matter jurisdiction over NWEA’s suit. The district court possessed subject matter jurisdiction over NWEA’s suit under the general federal question statute, 28 U.S.C. § 1331, unless another statute divested the district court of jurisdiction.[16] To determine whether the district court had been divested of jurisdiction, the Ninth Circuit examined section 509(b)(1) of the CWA, which specifies seven categories of agency action where the challenge must be brought in a court of appeals rather than a district court.

EPA claimed that NWEA’s ultra vires challenge fell within two categories under the CWA’s jurisdiction-divesting provisions, sections 509(b)(1)(E) and 509(b)(1)(F). In reviewing EPA’s allegations, the Ninth Circuit concluded the district court had subject matter jurisdiction over NWEA’s lawsuit because the agency action did not fall under either of these subsections. In reaching its decision, the Ninth Circuit looked first to section 509(b)(1)(E), which provides for review by the court of appeals of EPA actions in approving or promulgating effluent limitations under sections 301, 302, 306, and 405 of the CWA.[17] The court reasoned that because section 40 C.F.R. § 122.3(a) does not involve the approval or promulgation of an effluent limitation, but instead creates a categorical exception for three types of discharges, section 509(b)(1)(E) did not divest the district court of jurisdiction over NWEA’s challenge.

Second, the Ninth Circuit examined section 509(b)(1)(F), which provides for review of EPA actions in a court of appeals if the action involves issuing or denying a permit under section 402 of the CWA.[18] The court reasoned that because the three exemptions provided in the regulation were not explicitly contained in section 402 of the CWA, the case did not involve the issuing or denying of a permit, or a functionally similar action, under section 402. The Ninth Circuit determined that section 509(b)(1)(F) did not authorize original jurisdiction in the court of appeals for NWEA’s challenge because section 122.3(a) involves permanent categorical exemptions for three types of discharges from the permitting requirements-not the issuance or denial of a permit. Ultimately, the Ninth Circuit concluded that NWEA’s challenge did not fall under section 509(b)(1) of the CWA; consequently the district court had subject matter jurisdiction over the case.

The Ninth Circuit next turned to the issue of whether the statute of limitations barred the lawsuit. Under the applicable statute of limitations, civil actions commenced against the United States are barred unless the complaint is filed six years after the right of action first accrues.[19] The determination of whether the statute of limitations barred NWEA’s first cause of action depended on whether the right of action accrued in the 1970s, when EPA promulgated the regulation, or in 2003, when EPA denied NWEA’s petition. EPA conceded that the statute of limitations would not bar the suit if the right of action accrued in 2003. Looking to indistinguishable Ninth Circuit case law, the court determined that the date of the 2003 denial was the date of first accrual under the statute of limitations.[20] Therefore, NWEA timely filed their suit in the district court.

Next, the court addressed NWEA’s substantive ultra vires claim. NWEA’s first cause of action asserted the CWA does not authorize the exemption of vessel discharges found in 40 C.F.R. § 122.3(a) and that EPA acted ultra vires in promulgating the regulation. In its second cause of action, NWEA claimed that EPA did not act in accordance with the law when the agency denied its petition for rulemaking.

EPA countered with three arguments. First, because NWEA’s petition for rulemaking in 1999 challenged only the exclusion for ballast water provided in 40 C.F.R. § 122.3(a), the court should limit NWEA’s challenge to the ballast water exemption. Second, EPA argued that the CWA authorized EPA to promulgate section 122.3(a) or, alternatively, the statute is ambiguous and the court should defer to the agency’s interpretation. Third, EPA claimed that even if the CWA did not authorize the promulgation of section 122.3(a), Congress acquiesced to the regulation in post-1973 statutes.

In reviewing EPA’s first argument, the Ninth Circuit affirmed the decision of the district court to consider all three of the disputed exemptions in the regulation. Although NWEA was primarily concerned with the environmental effects of ballast water discharges, the court noted that NWEA consistently indicated that their overall goal was the repeal of all three exemptions. Additionally, EPA’s denial of NWEA’s petition explicitly noted that plaintiffs sought repeal of the entire regulation. As a result, the Ninth Circuit concluded the record contained sufficient evidence to show NWEA’s claim was not limited to ballast water discharges.

Second, the court examined the text of the CWA to determine whether section 122.3(a) was valid. When reviewing an agency’s construction of a statute, the court’s inquiry is guided by Chevron.[21] Under Chevron, the court first addresses whether Congress has spoken directly on the precise issue.[22] If the intent of Congress is clear, the court ends its inquiry and gives effect to Congress’ unambiguously expressed intent.[23]

Looking at the text of the CWA, the court first concluded that the plain meaning of the statute covers discharges from marine vessels. Under the CWA, the discharge of any pollutant from a point source into waters of the United States without a permit is unlawful.[24] Noting the definitions of point source, pollutant, and navigable waters, the court determined that vessel discharges clearly fall within the broad language of the CWA.

Having determined that vessel discharges are covered by the CWA, the court next examined whether the CWA authorized EPA to promulgate a regulatory exemption. Looking at section 402 of the CWA, the only possible source of authority for the exemption, the court determined that Congress did not give EPA authority to exempt entire categories of point source discharges from the permitting requirement. Section 402 of the CWA provides that the EPA Administrator “may, after opportunity for public hearing, issue a permit for the discharge of any pollutant, . . . notwithstanding section 301(a), upon condition that such discharge” will meet either all applicable requirements under the CWA or the conditions the Administrator determines are necessary to carry out the Act.[25] The Ninth Circuit reasoned that because section 402 uses the word “may,” but only in the context of issuing a permit for the discharge of any pollutant, Congress only intended to give the Administrator discretion to either issue a NPDES permit or apply the total prohibition on discharges found under section 301(a)-not to develop categorical exemptions from the permitting process. Therefore, Congress’ plain intent on the face of the Act requires permits in any situation that involves the discharge of pollutants from a point source into waters of the United States.

Next, the court turned to EPA’s contention that even if the CWA did not authorize EPA to develop three categorical exemptions for marine discharges, Congress subsequently acquiesced to EPA’s interpretation of the statute. Absent “overwhelming evidence” of congressional acquiescence, courts are extremely reluctant to replace the plain text and original understanding of a statute with a different agency interpretation.[26] Because the Ninth Circuit was unable to find overwhelming evidence of congressional acquiescence to section 122.3(a)’s exemptions in the statutes or legislative history discussed by EPA, it held that there was insufficient evidence to show Congress acquiesced to EPA’s ultra vires interpretation of the CWA.

EPA relied primarily on two statutes when arguing that Congress acquiesced to the regulation-the National Defense Authorization Act of 1996 (NDAA)[27] and the Deep Seabed Hard Mineral Resources Act of 1980 (DSHMRA).[28] In the NDAA, Congress expressly exempted discharges from the normal operation of military vessels from the permitting requirements of the CWA. A Senate report on the NDAA explained that section 122.3(a) was the regulatory basis for the exemption of most non-sewage discharges from vessels.[29] However, the Ninth Circuit concluded that the report did not endorse regulatory exemptions for categories of marine discharges. Instead, the court determined that, except for the statutory exemption provided in the NDAA, Congress intended that CWA’s permitting requirements would apply to military vessels.[30] As such, the Ninth Circuit concluded that the NDAA did not endorse section 122.3(a) and did not provide evidence that Congress intended to acquiesce to the regulation.

The Ninth Circuit next turned to DSHMRA, which requires vessels engaged in deep sea mining and drilling to comply with the CWA. Under section 122.3(a), marine vessels that are not engaged in transportation-related activities are not exempt from the permitting requirements of the CWA.[31] In examining the legislative history of DSHMRA, the court determined that Congress, at most, was aware of section 122.3(a) and explicitly approved of EPA’s decision not to exempt non-transportation marine vessels from the permitting process,[32] but that there was insufficient evidence to show Congress acquiesced to section 122.3(a).

EPA also relied on four additional statutes to show congressional acquiescence to the regulation: the Nonindigenous Aquatic Nuisance Prevention and Control Act of 1990 (NANPCA),[33] the National Invasive Species Act of 1996 (NISA),[34] the Act to Prevent Pollution from Ships (APPS),[35] and a statute regulating discharges by Alaskan cruise ships.[36] NANPCA and NISA address the problem of invasive species in ballast water discharges. However, the court concluded that the statutes merely indicated Congress’ desire to address the national problem of ballast water discharges of invasive species on multiple fronts. The statutes, therefore, did not provide overwhelming evidence of congressional acquiescence to EPA’s regulation. The Ninth Circuit also determined that the APPS, which implemented the International Convention for the Prevention of Pollution from Ships of 1973 and the Protocol of 1978 (known collectively as MARPOL 73/78), and the Alaskan cruise ship legislation, which regulates sewage and gray water discharges from cruise ships in Alaskan waters, both provide clauses that indicate nothing in the law should be construed as altering any other statute. Therefore, neither the APPS, nor the Alaskan cruise ship legislation, provided any indication of congressional intent to acquiesce to EPA’s regulation.

Lastly, the court affirmed the decision of the district court to vacate the challenged portions of the regulation and remand for further proceedings. The Ninth Circuit concluded that the district court’s remedy, which provided EPA with a two-year period in which to promulgate a new regulation, was a valid exercise of the court’s remedial powers. Additionally, having found the district court had jurisdiction over NWEA’s lawsuit, the Ninth Circuit dismissed the petition filed by NWEA in the court of appeals for lack of subject matter jurisdiction.

In summary, the Ninth Circuit held that EPA acted ultra vires in exempting certain vessel discharges under 40 C.F.R. § 122.3(a) and that EPA’s denial of the petition requesting repeal of the regulation was not in accordance with the law.


[1] Federal Water Pollution Control Act, 33 U.S.C. §§ 1251-1387 (2006).

[2] Id. § 1311(a).

[3] Id. § 1342.

[4] N. Plains Res. Council v. Fid. Exploration & Dev. Co., 325 F.3d 1155, 1160 (9th Cir. 2003).

[5] See National Pollutant Discharge Elimination System, 38 Fed. Reg. 13,528, 13,530 (May 22, 1973).

[6] 40 C.F.R. § 122.3(a) (2008).

[7] See Administrative Procedure Act, 5 U.S.C. § 706(2)(C) (2006) (regarding judicial review of agency actions “in excess of statutory jurisdiction, authority, or limitations, or short of statutory right”).

[8] Id. § 706(2)(A).

[9] At the remedy stage, six states-Illinois, Michigan, Minnesota, New York, Pennsylvania, and Wisconsin-intervened on the side of the plaintiffs to protect their interest in state waters.

[10] See, e.g., Ecology Ctr., Inc. v. U.S. Forest Serv., 192 F.3d 922, 924 (9th Cir. 1999).

[11] See, e.g., Sierra Club v. Penfold, 857 F.2d 1307, 1315 (9th Cir. 1988).

[12] See, e.g., Envtl. Prot. Info. Ctr. v. U.S. Forest Serv., 451 F.3d 1005, 1008 (9th Cir. 2006).

[13] See, e.g., Great Basin Mine Watch v. Hankins, 456 F.3d 955, 961 (9th Cir. 2006).

[14] 5 U.S.C. §§ 551-559, 701-706, 1305, 3105, 3344, 4301, 5335, 5362, 7521 (2006).

[15] See id. § 706(2)(C).

[16] See 28 U.S.C. § 1331 (2006).

[17] Federal Water Pollution Control Act, 33 U.S.C. § 1369(b)(1)(E) (2006).

[18] Id. § 1369(b)(1)(F).

[19] See 28 U.S.C. § 2401(a) (2000).

[20] See Wind River Mining Corp. v. United States, 946 F.2d 710, 716 (9th Cir. 1991) (holding that the right to bring a civil suit challenging agency action accrues at time of final administrative action).

[21] See Chevron U.S.A., Inc. v. Natural Res. Def. Council, 467 U.S. 837, 842-43 (1984).

[22] Id.

[23] Id.

[24] See Comm. to Save Mokelumne River v. E. Bay Mun. Util. Dist., 13 F.3d 305, 307 (9th Cir. 1993).

[25] Federal Water Pollution Control Act, 33 U.S.C. § 1342(a)(1) (2006).

[26] See, e.g., Solid Waste Agency of N. Cook County v. U.S. Army Corps of Eng’rs, 531 U.S. 159, 170 n.5 (2001).

[27] 33 U.S.C. §§ 1322(a), (j), (n), 1362(6) (2000).

[28] 30 U.S.C. §§ 1401-1473 (2000)

[29] See S. Rep. No. 104-113, at 12 (1995).

[30] Id. at 3.

[31] 40 C.F.R. § 122.3(a).

[32] See S. Rep. No. 96-360, at 2-3 (1979); see also id. at 3 (noting that DSHMRA merely “clarif[ied] the application of section 402″ to these vessels).

[33] 16 U.S.C. §§ 4701-4751 (2000).

[34] Pub. L. No. 104-332, 110 Stat. 4073 (1996) (amending NANPCA).

[35] Act to Prevent Pollution from Ships of 1980, 33 U.S.C. §§ 1901-1915 (2000).

[36] Consolidated Appropriations Act of 2001, Pub. L. No. 106-554 § 1(a)(4), 114 Stat. 2763.

North Idaho Community Action Network v. U.S. Department of Transportation

North Idaho Community Action Network (NICAN) challenged a proposed highway construction project on U.S. Highway 95 in northern Idaho, alleging the defendant agencies[1] (collectively USDOT) violated the National Environmental Policy Act (NEPA)[2] and the Department of Transportation Act (DTA).[3] The United States District Court for the District of Idaho granted summary judgment in favor of defendants, and NICAN appealed. The Ninth Circuit affirmed as to the NEPA claims, holding that USDOT: 1) fulfilled its obligations under NEPA’s alternatives provision, 2) comported with NEPA by taking a hard look at dredging impacts, 3) did not violate NEPA by failing to consider a tunnel alternative, 4) sufficiently considered impacts to historical properties, and 5) did not violate NEPA by failing to issue a supplemental environmental impact statement. The Ninth Circuit reversed as to one of the two DTA claims, holding that USDOT violated the statute by issuing a record of decision prior to evaluating impacts of all project phases on historical properties, and affirmed as to the other, holding that formal evaluation of historical properties was not required for project modifications.

USDOT proposed a four-phase construction project (the Project) to improve U.S. Highway 95 in and around Sandpoint, Idaho. The first, second, and fourth phases involved widening the highway to four lanes; the third phase involved realigning a two-mile stretch of the highway to bypass downtown Sandpoint. USDOT approved a final environmental impact statement (EIS) in September 1999 and issued a record of decision for the Project in May 2000. USDOT released an environmental assessment (EA) in April 2005 that included design changes related to the third phase of the project (Sand Creek Byway). The 2005 EA concluded the changes would not have significant impacts beyond those already considered. Based on this conclusion, USDOT issued a finding of no significant impact (FONSI). USDOT then prepared an environmental reevaluation in August 2006 (Reevalution), setting forth additional changes to project design, including the dredging of Sand Creek, and assessing their possible environmental effects. The 2006 Reevaluation concluded there was no additional significant impact and that neither a supplemental environmental impact statement (SEIS) nor a further EA was required. NICAN challenged USDOT’s approval of the Project in district court in July 2005, after the 2005 EA and FONSI but before preparation of the 2006 Reevaluation. Reviewing the district court’s grant of summary judgment de novo[4] for arbitrary and capricious action by USDOT,[5] the Ninth Circuit began by addressing NICAN’s five NEPA claims.

First, NICAN argued that USDOT violated NEPA because the 2005 EA did not consider alternatives to the project design changes described in the 2005 EA. The Ninth Circuit disagreed, holding that USDOT fulfilled its obligations under NEPA when it considered and discussed two alternatives in the 2005 EA: the Project with the design changes proposed in the 2005 EA and the Project as described in the 1999 EIS. NEPA requires agencies to “study, develop, and describe appropriate alternatives to recommended courses of action in any proposal which involves unresolved conflicts concerning alternative uses of available resources.”[6] Although an agency’s obligation to consider alternatives applies whether an agency is preparing an EIS or an EA, “an agency’s obligation to consider alternatives under an EA is a lesser one than under an EIS.”[7] An agency is required to “[r]igorously explore and objectively evaluate all reasonable alternatives”[8] for an EIS but is only required to include a brief discussion of reasonable alternatives for an environmental assessment.[9] Here, the Ninth Circuit held that because “the design changes to the Project proposed in the 2005 EA will not result in significant environmental effects that were not previously evaluated in the 1999 EIS,” USDOT’s brief discussion of only two alternatives was sufficient under NEPA.[10]

Second, NICAN argued that USDOT violated NEPA by failing to disclose and assess the impacts of dredging Sand Creek in the 2005 EA or in a supplemental EA. The Ninth Circuit disagreed, holding that USDOT did not act arbitrarily or capriciously in making the determinations and that it complied with NEPA in its evaluation of the proposed dredging. The factual record indicated there was not enough information about dredging and its possible impacts at the time USDOT prepared the 2005 EA. After more information became available, USDOT performed the 2006 Reevaluation and concluded that dredging would not have significant environmental impacts beyond those already identified. The court was satisfied that USDOT took the requisite “hard look” at the impacts of dredging in the 2006 Revaluation and that USDOT properly concluded that nothing in the Reevaluation necessitated a SEIS or supplemental EA.[11]

Third, NICAN argued that USDOT violated NEPA by failing to consider a tunnel alternative for the Project which was not identified until June 2006. The Ninth Circuit disagreed, holding that NEPA’s mandate to consider new information extends only to information or circumstances regarding environmental impacts that may not have been appreciated or considered when the EIS was prepared and does not extend to new alternatives absent “substantial changes in the proposed action relevant to environmental concerns.”[12] Here, the tunnel alternative and its environmental impacts were neither new information nor a new circumstance not considered when the 1999 EIS was prepared; nor was there a substantial change to the Project relevant to environmental concerns. Accordingly, the Ninth Circuit concluded USDOT did not violate NEPA by failing to consider the tunnel alternative.

Fourth, NICAN argued that USDOT violated NEPA by 1) taking a phased approach to the Project’s impact on historic properties and 2) failing to take a “hard look” at how the construction and operation of the project would affect the Burlington Northern Railroad Depot. The Ninth Circuit disagreed, holding USDOT’s broad overview in the 1999 EIS of the Project’s impacts on historic properties, coupled with the specific and detailed analysis of the impacts of the Sand Creek Byway, was more than sufficient to meet NEPA’s requirements regarding historic properties. The court explained that “NEPA requires federal agencies to consider the environmental impact of major federal actions” but imposes no independent requirement that an agency examine nonenvironmental impact of federal actions on historic properties.[13]

Fifth, NICAN argued that USDOT violated NEPA by failing to prepare an SEIS. The Ninth Circuit disagreed, holding that USDOT’s determination that the changes to the Project would not significantly impact the environment in a way not previously considered, and therefore an SEIS was not required, and was not arbitrary or capricious. An agency is required to prepare an SEIS only if changes, new information, or circumstances may result in significant environmental impacts “in a manner not previously evaluated and considered.”[14] An agency may prepare an environmental report or an EA to assist it in determining whether an SEIS is required.[15] Here, USDOT considered the changes to the Project and their impacts in both an EA and a Reevaluation, but determined those impacts were not sufficiently significant or adverse to require an SEIS. Specifically, construction of 1.1 acres of additional wetland area mitigated the 0.32 additional acres of wetlands affected by the modified Project. The court also noted the impacts of the Project were considered in the 1999 EIS, the 2005 EA, and the 2006 Reevaluation. Cumulatively, the court said, these documents showed that USDOT sufficiently considered environmental impacts.

The Ninth Circuit next considered the alleged violations of the DTA.[16] NICAN argued that USDOT violated section 4(f) the DTA 1) by failing to survey, identify, and evaluate historical properties for all four phases of the project, and 2) by determining that a DTA analysis was not required because the construction and operation of the project would not result in “use” of the historic property. Section 4(f) allows for a federal project “requiring the use of land of an historic site” to be approved only if “there is no prudent and feasible alternative to using that land and the program or project includes all possible planning to minimize harm to the park, recreation area, wildlife and waterfowl refuge, or historic site resulting from the use.”[17] The Ninth Circuit reversed on the first issue raised by NICAN, holding that an agency is required to complete the section 4(f) evaluation for the entire project prior to issuing its record of decision.

In considering the proper remedy for this violation, the Ninth Circuit determined that, while the agencies had technically violated the DTA by issuing a record of decision before completing the section 4(f) evaluation for the entire Project, “the scope of injunctive relief should be limited to precluding the [USDOT] from commencing construction of the remaining three phases of the Project until the section 4(f) evaluation has been fully completed.”[18] The Ninth Circuit reasoned that because all parties agreed the section 4(f) evaluation had been fully completed for the Sand Creek Byway phase of the project, it was unnecessary to enjoin that portion of the Project.

The Ninth Circuit affirmed on the second DTA issue, holding USDOT did not act arbitrarily or capriciously in determining that modifications to the Project discussed in the 2005 EA would not “use” the depot property within the meaning of section 4(f). The court explained that the modifications at issue were either improvements which would benefit the Depot and thus not permanently incorporate the Depot property into a transportation facility,[19] or temporary and minor improvements which properly constituted a temporary occupancy, and not a “use” under section 4(f).[20]

In summary, the Ninth Circuit affirmed the decision of the district court as to the NEPA claims, reversed and remanded the DTA claim regarding issuance of a record of decision with instructions to the district court to enter a limited injunction, and affirmed as to USDOT’s evaluation of historical properties for modifications under the DTA.


[1] Defendants were the United States Department of Transportation, the Federal Highway Administration, the United States Fish & Wildlife Service, and the Idaho Transportation Department.

[2] National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4370e (2006).

[3] Department of Transportation Act of 1966, 49 U.S.C. § 303(c) (2006).

[4] Nw. Ecosystem Alliance v. U.S. Fish & Wildlife Serv., 475 F.3d 1136, 1140 (9th Cir. 2007).

[5] Administrative Procedure Act, 5 U.S.C. § 706(2)(A) (2006) (allowing a reviewing court to set aside agency actions that are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law”).

[6] 42 U.S.C. § 4332(E) (2006).

[7] N. Idaho Cmty. Action Network v. U.S. Dep’t of Transp. (North Idaho), 545 F.3d 1147, 1153-54 (9th Cir. 2008)(citing Native Ecosystems Council v. U.S. Forest Serv., 428 F.3d 1233, 1246 (9th Cir. 2005)).

[8] See 40 C.F.R. § 1502.14(a) (2008).

[9] See id. § 1508.9(b).

[10] See Native Ecosystems Council v. U.S. Forest Serv., 428 F.3d 1233, 1245-49 (9th Cir. 2005) (holding that agency complied with NEPA’s alternatives provision in preparing an environmental assessment where the agency considered only two alternatives).

[11] See Price Road Neighborhood Ass’n v. U.S. Dep’t of Transp., 113 F.3d 1505, 1510 (9th Cir. 1997)(holding that an agency is in full compliance with NEPA and is not required to conduct a supplemental EA if the agency takes the requisite “hard look” and determines that the new impacts will not be significant or significantly different from those already considered).

[12] NEPA requires agencies to prepare supplements to either draft or final environmental impact statements if “[t]here are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts.” See 40 C.F.R. § 1502(c)(1)(ii) (2008).

[13] North Idaho, 545 F.3d 1147, 1156 (9th Cir. 2008)(citing San Carlos Apache Tribe v. United States, 417 F.3d 1091, 1097 (9th Cir. 2005)).

[14] Westlands Water Dist. v. Dep’t of Interior, 376 F.3d 853, 873 (9th Cir. 2005).

[15] See 23 C.F.R. §§ 771.119(a), 771.129,771.130(c) (2008).

[16] Department of Transportation Act of 1966, 49 U.S.C. § 303(c) (2006).

[17] Id.

[18] North Idaho, 545 F.3d at 1160-61.

[19] 23 C.F.R. § 771.135(p)(1) (2000)(repromulgated at 23 C.F.R. § 771.17 (2008)).

[20] Id.

Natural Resources Defense Council v. U.S. Environmental Protection Agency

Environmental organizations Natural Resources Defense Council and Waterkeeper Alliance (collectively Plaintiffs) brought suit against the U.S. Environmental Protection Agency (EPA), alleging EPA violated the Clean Water Act (CWA)[1] and the Administrative Procedure Act (APA)[2] by failing to promulgate regulations for stormwater pollution discharges caused by the construction and development industry. The U.S. District Court for the Central District of California granted Plaintiffs’ motion for partial summary judgment and issued a permanent injunction compelling EPA to issue effluent limitation guidelines (ELGs) and new source performance standards (NSPSs) for the construction industry. EPA appealed, challenging the district court’s jurisdiction, Plaintiffs’ standing to sue, and the grant of partial summary judgment in favor of Plaintiffs. The Ninth Circuit affirmed, holding the district court properly exercised jurisdiction over Plaintiffs’ claim; Plaintiffs had standing to sue; and EPA had a mandatory duty under the CWA to promulgate ELGs and NSPSs for the construction industry.

The CWA prohibits the discharge of any pollutant from a point source into the navigable waters of the United States without a National Pollutant Discharge Elimination System (NPDES) permit.[3] NPDES permits establish limits on the type and quantity of pollutants that can be released into waters; these limits are determined according to more specific guidelines-ELGs and NSPSs-which are promulgated by EPA. Under section 304(m) of the CWA, every two years EPA must publish a plan in the Federal Register identifying categories of sources that discharge toxic or nonconventional pollutants and establish a schedule for promulgating ELGs and NSPSs for the categories identified.[4] In 2000, EPA’s plan identified construction activities as a point source category, thus requiring the promulgation of guidelines under section 304(m).

Two years later, EPA issued a proposed rule to address stormwater discharge from construction sites which identified three options under consideration by the agency.[5] In 2004, EPA withdrew its proposed ELGs and NSPSs for the construction and development industry and decided instead to establish no new requirements to control stormwater runoff from construction sites. EPA explained its decision by stating that existing NPDES regulations adequately addressed stormwater discharge for most construction sites and that the cost was “simply too high” relative to the expected benefits to be achieved by the proposed ELGs.[6] EPA removed the construction industry from subsequent section 304(m) plans in 2004 and 2006; the latter plan stated EPA “mistakenly” identified the construction industry in its 2002 plan and corrected its own mistake by removing the industry from its 2004 plan.[7]

Plaintiffs subsequently brought suit against EPA to challenge its decision not to issue ELGs and NSPSs for the construction industry after it had listed construction activities as a point source category under section 304(m).[8] Defendants moved to dismiss, claiming the district court lacked jurisdiction over Plaintiffs’ claim and that Plaintiffs lacked standing. The states of Connecticut and New York (state-intervenors) intervened on behalf of Plaintiffs, and the National Association of Home Builders and the Associated General Contractors of America (industry-intervenors) did the same on behalf of Defendants. The district court denied defendants’ motion to dismiss and granted Plaintiffs’ motion for summary judgment. The district court also issued a permanent injunction requiring EPA to establish ELGs and NSPSs for the construction industry by December 1, 2009. Defendants appealed.

Reviewing the district court’s assertion of jurisdiction and interpretation of the CWA de novo, the Ninth Circuit first considered whether the district court properly exercised its original jurisdiction.[9] Section 505(a)(2) of the CWA grants the district court original and exclusive jurisdiction over suits “against the Administrator where there is alleged a failure . . . to perform any act or duty under this chapter which is not discretionary.”[10] Section 509(b)(1), in contrast, grants the courts of appeal jurisdiction to “[r]eview . . . the Administrator’s action . . . in approving or promulgating any effluent or other limitation.”[11] EPA argued the latter provision applied and that the court of appeals had exclusive original jurisdiction. The Ninth Circuit disagreed, holding that district courts have exclusive jurisdiction “where a plaintiff alleges that the EPA has failed to perform a non-discretionary duty under the CWA and the plaintiff does not challenge the substance of any existing regulations.”[12] Because Plaintiffs did not challenge the substance of any existing regulations, but rather, EPA’s failure to issue such regulations, section 509(b)(1) was inapplicable, and the district court had original jurisdiction pursuant to section 505(a)(2).

In support of its holding, the court relied on recent Ninth Circuit precedent in the case of Our Children’s Earth Foundation v. EPA (OCEF).[13] The OCEF plaintiffs similarly challenged EPA’s failure to timely review effluent guidelines and limitations under the CWA.[14] The court affirmed the district court’s jurisdiction under section 505(a)(2) and stated section 509(b)(1) “extends only to a substantive review of . . . guidelines actually promulgated, and not to the threshold question of whether the statutory requirements of the CWA have been met.”[15] In further support of its analysis, the Ninth Circuit cited a Third Circuit case in which plaintiffs sought to compel EPA to perform its nondiscretionary duty to promulgate NSPSs for the coal mining industry.[16] The Third Circuit concluded that jurisdiction was proper under section 505(a)(2) because section 509 focuses on the substance or effect of existing regulations, not on a petitioner’s request to compel EPA to promulgate new or different limitations.[17] Based on the foregoing, the Ninth Circuit held the district court properly exercised it jurisdiction over Plaintiffs’ claim that EPA violated its statutory mandate to promulgate ELGs and NSPSs for the construction industry.

On appeal, industry-intervenors further challenged whether Plaintiff organizations had standing to sue on behalf of their members.[18] Under Article III’s standing requirements, a plaintiff must show it has suffered an injury in fact, which is concrete and particularized and actual or imminent.[19] The party must further demonstrate the injury is fairly traceable to the conduct of the defendant and is likely to be redressed by a favorable decision.[20]

Applying the three-prong standing analysis, the Ninth Circuit concluded that members of the environmental groups had demonstrated they suffered an injury in fact because they submitted declarations attesting they had used particular waterways for aesthetic and recreational purposes and that their use and enjoyment had been diminished by stormwater discharges from construction sites flowing directly into these waterways.

Next, addressing the second and third prongs of traceability and redressability, the Ninth Circuit analyzed whether Plaintiffs’ injuries were traceable to EPA’s failure to promulgate ELGs and NSPS and would be redressed by EPA’s promulgation of these regulations. The court recognized that redressability could not be precisely determined absent knowledge of the actual substance of EPA’s regulations. However, the court concluded Plaintiffs made a sufficient showing that the type of stormwater discharge causing injury is that which the ELGs and NSPSs aim to address, and that such regulations are likely to reduce the risk of injury-causing pollution. In support of its analysis, the court first relied on a number declarations submitted by Plaintiffs’ members, which supported that stormwater discharges from construction sites into bodies of water that they use and enjoy were polluting and diminishing the water quality. Second, the Ninth Circuit explained that by requiring effluent limitations for identified point sources, Congress expressed its view that ELGs and NSPSs reduce the risk of the type of pollution causing members’ injury. According to the court, “Where Congress has expressed the need for specific regulations relating to the environment, that expression supports an inference that there is a causal connection between the lack of those regulations and adverse environmental effects.”[21] Based on these considerations, the court held that the environmental-group Plaintiffs had standing to bring suit.

Having concluded that jurisdiction was proper and Plaintiffs had standing to sue, the Ninth Circuit last reviewed de novo the district court’s grant of partial summary judgment[22] and accompanying interpretation of the CWA.[23] In analyzing EPA’s statutory duty to promulgate ELGs and NSPSs, the court reviewed EPA’s construction of the CWA under Chevron U.S.A., Inc. v. Natural Resources Defense Council (Chevron)[24] and held that once EPA listed the construction industry as a point source category, the agency was required to promulgate ELGs and NSPSs. Applying step one of Chevron, the court concluded that the language of the CWA clearly establishes that EPA must promulgate effluent limitations and standards for all point source categories it lists in section 304(m) plans. Further, by requiring EPA to “establish a schedule” under which the guidelines shall be promulgated “no later than . . . 3 years after the publication of the plan,” under section 304(m), Congress unequivocally expressed its intent that the promulgation of ELGs and NSPSs was mandatory.[25]

After holding that EPA had a nondiscretionary duty to promulgate ELGs and NSPSs, the Ninth Circuit considered whether EPA properly avoided this duty by removing the construction industry from its 2004 and 2006 section 304(m) plans. In addition to finding nothing in the CWA granting EPA authority to remove a point source category from its published plans, the court further found EPA’s position-that it was allowed under the CWA to unilaterally de-list a point source category-to be an impermissible construction of the statute. The court reasoned that the congressional mandate to promulgate guidelines no later than three years after publication would be rendered meaningless if EPA could avoid the deadline by unilaterally de-listing any category of point sources. Thus, the court concluded, the three-year period provided for in section 304(m)(1)(c) is designed to give time to determine the substance of the effluent limitations and standards, not for consideration of whether to develop ELGs for a category of point source; the latter decision is made when EPA lists the point source in the section 304(m) plan.

Based on the foregoing, the Ninth Circuit affirmed the district court’s grant of partial summary judgment in favor of Plaintiffs and its injunction requiring EPA to issue ELGs and NSPSs for the construction industry no later than December 1, 2009.


[1] Federal Water Pollution Control Act, 33 U.S.C. §§ 1251-1387 (2006).

[2] 5 U.S.C. §§ 551-559, 701-706, 1305, 3105, 3344, 4301, 5335, 5362, 7521 (2006).

[3] 33 U.S.C. §§ 1311(a), 1342 (2006).

[4] Id. § 1314(b).

[5] EPA’s options included 1) establishing minimum requirements for conducting site inspections and providing certifications regarding designs and controls required by the NPDES authority, 2) establishing ELGs in addition to the minimum requirements of option one, and
3) establishing no new requirements and instead leaving control and certification requirements to the best professional judgment of the permitting authority. Construction and Development Category, 67 Fed. Reg. 42,644, 42,644 (proposed June 24, 2002).

[6] Effluent Limitations Guidelines and New Source Performance Standards for the Construction and Development Category, 69 Fed. Reg. 22,472, 22,477 (Apr. 26, 2004). EPA estimated that the annual cost of the proposed ELGs would exceed $500 million and would displace a number of workers in the construction industry. Id. at 22,478.

[7] Notice of Availability of Final 2006 Effluent Guidelines Program Plan, 71 Fed. Reg. 76,644, 76,644-45 (Dec. 1, 2006).

[8] 33 U.S.C. § 1314(b) (2006).

[9] United States v. Bennett, 147 F.3d 912, 913 (9th Cir. 1998) (indicating that district court’s assumption of jurisdiction is reviewed de novo);League of Wilderness Defenders-Blue Mountains Biodiversity Project v. Forsgren, 309 F.3d 1181, 1183 (9th Cir. 2002) (indicating that district court’s interpretation of CWA is reviewed de novo).

[10] 33 U.S.C. § 505(a)(2) (2006).

[11] Id. § 509(b)(1).

[12] Natural Res. Def. Council v. U.S. Envtl. Prot. Agency (NRDC v. EPA), 542 F.3d 1235, 1242 (9th Cir. 2008).

[13] 527 F.3d 842 (9th Cir. 2008).

[14] Id. at 844.

[15] Id. at 847.

[16] Pa. Dep’t of Envtl. Res. v. U.S. Envtl. Prot. Agency, 618 F.2d 991, 993 (3d Cir. 1980). The Ninth Circuit also distinguished a Tenth Circuit decision, Maier v. EPA, 114 F.3d 1032 (10th Cir. 1997), in which the plaintiffs challenged the inadequacy of existing regulations as part of a challenge to EPA’s denial of a petition to initiate CWA rulemaking proceedings. The Ninth Circuit explained that, in Maier, the Tenth Circuit was concerned with evasion of jurisdiction by the court of appeals via artful pleading of a claim as a failure to revise rather than a challenge to the substance of the regulation. Id. at 1038.

[17] Pa. Dep’t of Envtl. Res., 618 F.2d at 996.

[18] Defendant EPA did not challenge Plaintiffs’ standing on appeal. The Ninth Circuit reviewed industry-intervenors’ challenge to Plaintiffs’ standing de novo. Buono v. Norton, 371 F.3d 543, 546 (9th Cir. 2004).

[19] Lujan v. Defenders of Wildlife, 504 U.S. 555, 560-61 (1992).

[20] Id.

[21] NRDC v. EPA, 542 F.3d at 1248 (9th Cir. 2008); see also Nat’l Wildlife Fed’n v. Hodel, 839 F.2d 694, 708 (D.C. Cir. 1998);Alaska Ctr. for the Env’t v. Browner, 20 F.3d 981, 984-85 (9th  Cir. 1994).

[22] Buono v. Norton, 371 F.3d 543, 545 (9th Cir. 2004) (reviewing district court’s grant of summary judgment de novo).

[23] League of Wilderness Defenders-Blue Mountains Diversity Project, 309 F.3d 1181, 1183 (9th Cir. 2002) (reviewing district court’s interpretation of the CWA de novo).

[24] 467 U.S. 837 (1984).

[25] Federal Water Pollution Control Act, 33 U.S.C. § 1314(b) (2006).

Lands Council v. McNair

Nonprofit organizations Lands Council and the Wild West Institute (collectively Lands Council) sought a temporary restraining order and preliminary injunction against the United States Forest Service’s (USFS) Mission Brush Project (MBP), which allowed selective logging of 3829 acres of the Idaho Panhandle National Forest (IPNF).[1] Lands Council asserted that the MBP violated the Administrative Procedure Act (APA),[2] the National Forest Management Act (NFMA),[3] the National Environmental Policy Act (NEPA),[4] and Standard 10(b) of the IPNF Forest Plan.[5] The United States District Court for the District of Idaho denied Lands Council’s motion, ruling that Lands Council had not 1) demonstrated a likelihood of success on the merits and a possibility of irreparable injury, nor 2) shown that the balance of hardships tipped sharply in its favor. On appeal, a three-judge panel of the Ninth Circuit reached the opposite conclusion with regard to Land Council’s NFMA and NEPA claims and remanded for entry of a preliminary injunction.[6]

After reviewing the three-judge panel’s decision, an en banc Ninth Circuit panel concluded that the district court did not abuse its discretion, vacated the three-judge panel’s decision, and affirmed the district court’s denial of Lands Council’s preliminary injunction motion. The en banc panel first held that NFMA does not require USFS to always verify its methodology with on-the-ground analysis, overruling Ecology Center, Inc. v. Austin.[7] Instead, USFS must simply support conclusions with studies the agency, in its expertise, deems reliable. The court also overruled the suggestion from Idaho Sporting Congress v. Thomas[8] that habitat could not be used as a proxy for species viability under NFMA, holding that USFS can use habitat as a proxy to establish a species’ viability when the disturbance does not reduce suitable habitat in a way that threatens that species’ viability. Furthermore, the Ninth Circuit held that USFS satisfied NEPA by conducting a “full and fair discussion” of environmental impacts of the MBP.[9] Finally, the court concluded that Lands Council failed to show that the balance of hardships tipped sharply in its favor.

In 2002, USFS began forest management planning for the Mission and Brush Creek areas of the IPNF, home to old growth trees, as well as a variety of animal and plant species and habitats. Fire suppression, logging, and disease changed the historic composition of the forest from relatively open stands of ponderosa pine and mature Douglas fir stands to the current composition of shade-tolerant younger Douglas firs stands and other mid-to-late successional species that crowd the forest. The court concluded that “[t]he increased density of trees has proven deleterious to the old growth trees” and threatened the area’s ecology.[10] Thus, USFS sought to restore the forest to more historic compositions of open ponderosa pine and Douglas fir stands. Additionally, USFS proposed to restore forest health and wildlife habitat, improve water quality and aquatic habitat, and provide for recreation activities.[11]

To accomplish these varied objectives, USFS proposed silvicultural treatments,[12] fuels treatments, and ecosystem burns on portions of the IPNF. USFS planned to perform treatments within 277 acres of old growth stands without harvesting old growth trees and expected the MBP to generate 23.5 million board feet of timber to be sold pursuant to three timber sale contracts.[13]

After publishing a draft environmental impact statement (EIS) and receiving comments, USFS released a FEIS and record of decision (ROD) in June 2004. Lands Council appealed the ROD, and USFS upheld the MBP. However, because of a Ninth Circuit decision addressing a different forest management project in the IPNF,[14] USFS ordered the preparation of a supplemental EIS. After a draft and public comment, USFS issued the supplemental final environmental impact statement (SFEIS) and ROD in April 2006. Lands Council filed an administrative appeal again, and USFS again upheld the MBP.

In October 2006, Lands Council filed suit in district court, moving for a preliminary injunction. After the district court denied its motion, Lands Council timely appealed to the Ninth Circuit, arguing that 1) under NFMA, USFS failed to demonstrate the reliability of the scientific methodology underlying its analysis of the MBP’s effect on wildlife and failed to comply with Standard 10(b) of the IPNF Forest Plan’s requirement to maintain ten percent old growth throughout the forest, and 2) under NEPA, USFS did not adequately address uncertainty regarding its proposed treatment as a strategy to maintain species viability. Initially, a three-judge panel reversed the district court’s decision and remanded for entry of a preliminary injunction.[15] The injunction prohibited USFS from 1) logging fourteen acres of old growth trees in the Haller Down Sale, and 2) taking action in the area of the Mission Fly By Sale.[16] However, the Ninth Circuit subsequently convened en banc to rehear the case and “clarify some of [its] environmental jurisprudence” regarding review of USFS action.[17]

The en banc panel reviewed the district court’s denial of Lands Council’s motion for abuse of discretion.[18] Using this deferential standard, the Ninth Circuit evaluated whether Lands Council demonstrated either 1) “a likelihood of success on the merits and the possibility of irreparable injury,” or 2) “that serious questions going to the merits were raised and the balance of hardships tips sharply in [Lands Council's] favor.”[19] To determine whether Lands Council was likely to prevail on the merits of its NFMA and NEPA claims, the Ninth Circuit applied the APA’s “arbitrary and capricious” standard.[20] Thus, the abuse of discretion review for the preliminary injunction incorporated the “arbitrary and capricious” standard.

The Ninth Circuit characterized Lands Council’s appeal as asking the court “to act as a panel of scientists” in reviewing USFS action.[21] The court admitted that it may have entertained such a broad standard of review in previous NFMA cases; however, the en banc panel sought to correct its jurisprudential inconsistencies by first discussing the language and purpose of NFMA and the court’s misconstruction of NFMA in an earlier case, Ecology Center, Inc. v. Austin,[22] before evaluating the Lands Council’s claims.

NFMA contains procedural and substantive requirements to guide USFS in managing the National Forest System. Procedurally, NFMA requires USFS to develop a forest plan for each unit of national forest.[23] Once a plan is developed, each subsequent agency action, including site-specific plans, must be consistent with the governing plan and comply with NFMA.[24] NFMA substantively requires USFS to develop guidelines to provide for “diversity of plant and animal communities based on the suitability and capability of the specific land area in order to meet overall multiple-use objectives.”[25] NFMA also requires consistency between the MBP and the IPNF Forest Plan, which requires USFS to manage the habitat of designated “sensitive” species, such as the flammulated owl, in a way that prevents further declines in population.[26] In addition to wildlife viability considerations, the Ninth Circuit stressed USFS must provide for multiple use[27] and “balance competing demands in managing National Forest System lands.”[28]

Before addressing Lands Council’s appeal, the Ninth Circuit overruled Ecology Center, reasoning that it had misconstrued the requirements of NFMA and disregarded well-established law governing the court’s review of agency decision making. In Ecology Center, the Ninth Circuit required USFS to “conduct on-the-ground analysis to verify its soil quality analysis and to establish the reliability of its hypothesis that treating old growth forest is beneficial to dependent species.”[29] First, the Ninth Circuit noted that Lands Council v. Powell (Lands Council I),[30] which required on-site spot verification of spreadsheet modeling, was “limited to the circumstances of that case;”[31] thus, when Ecology Center, relying on Lands Council I, imposed a categorical requirement of on-the-ground analysis, it established an overreaching rule. Next, the Ninth Circuit decided that NFMA, the IPNF Forest Plan, and relevant regulations, contrary to the court’s holding in Ecology Center, did not require that site-specific plans contain on-site analysis in consideration of wildlife viability. Instead, USFS can use any methodology or evidence to consider wildlife viability that it deems appropriate. Finally, the Ninth Circuit described Ecology Center as an example of the court’s failure to grant proper deference to USFS under the APA’s arbitrary and capricious standard of review. The court reasoned that it had no “proper role” in assessing the reliability or significance of USFS’s project analysis,[32] especially with respect to its predictions[33] or decisions involving a “high level of technical expertise.”[34] In overruling Ecology Center, the court held that under its new approach, “[USFS] must support its conclusions that a project meets the requirements of the NFMA and relevant Forest Plan with studies that the agency, in its expertise, deems reliable.”[35]

After overruling Ecology Center, the Ninth Circuit addressed Lands Council’s NFMA claim under the arbitrary and capricious standard. Lands Council argued that USFS violated NFMA by failing to establish the reliability of the data underlying its analysis of the MBP’s effect on wildlife, specifically the MBP’s effect on the sensitive flammulated owl and its habitat. USFS had conducted three studies documenting that flammulated owls prefer old growth habitat, as well as a study suggesting that flammulated owls live in old growth habitat even after it has been treated. Additionally, USFS conducted one on-the-ground survey of flammulated owls in an adjacent, treated forest plot and received one flammulated owl response as recent as 2006. Finally, USFS used a habitat suitability model, relying on vegetation characteristics, site visits, and aerial photographs to predict the treatment’s effect on flammulated owl habitat. On this record, USFS concluded that the MBP 1) would not decrease suitable habitat in the short-term, even if harvesting resulted in short-term negative effects, 2) would promote the viability of suitable habitat for the flammulated owl in the long-term, and 3) would not cause a loss of species viability or increase the likelihood of listing under the Endangered Species Act (ESA).[36]

Based on the USFS studies and the agency’s reasonable assumptions, the Ninth Circuit concluded that USFS did not act arbitrarily and capriciously in determining that the MBP satisfied NFMA and the IPNF Forest Plan regarding species diversity. For example, although the court described USFS’s survey for the flammulated owl at a nearby forest plot as “sparse” and “approaching the limits of [the court's] deference,”[37] the court reiterated that on-the-ground analysis was not required, and concluded, nonetheless, that there was sufficient evidence to defer to the USFS. Additionally, the court emphasized that “neither NFMA nor the IPNF Forest Plan require [USFS] to improve a species habitat to prove that it is maintaining wildlife viability.”[38] The court accepted USFS’s analysis of suitable habitat as a proxy for the viability of the flammulated owl, reasoning that Lands Council’s claims echoed arguments made in Inland Empire Public Lands Council v. USFS (Inland Empire).[39] In Inland Empire the Ninth Circuit approved USFS’s “habitat viability analyses,” which measured suitable habitat as a proxy to estimate a species’ population.[40] In this case, the Ninth Circuit noted that USFS similarly documented the quality and quantity of habitat necessary for the flammulated owl, as well as the habitat currently suitable and the estimated habitat suitable after the MBP.

The Ninth Circuit also discussed the effect, if any, a habitat disturbance, such as a timber harvest, had on its review of USFS under the “arbitrary and capricious” standard. The court overruled an earlier case, Idaho Sporting Congress v. Thomas,[41] to the extent it stood for the proposition that habitat could not be used as a proxy approach in the event of an “appreciable habitat disturbance.”[42] The Ninth Circuit reasoned that habitat disturbances do not inevitably indicate that a species’ viability will be threatened, and thus do not preclude USFS from using the habitat model as a population proxy when a disturbance does not reduce habitat to a point that threatens a species’ viability. However, USFS’s use of habitat as a proxy may be limited when the record 1) fails to establish a clear relationship between the habitat and the species at issue,[43] 2) fails to describe the types and amounts of habitat necessary to sustain a species’ viability,[44] or 3) suggests that the agency used outdated or inaccurate information for its habitat calculations.[45] In the present case, the Ninth Circuit determined that, based on USFS’s studies, surveys, and reasonable assumptions, the agency was not arbitrary and capricious in determining that the MBP will maintain a suitable habitat for a viable population of flammulated owls. Thus, the court concluded that the district court did not abuse its discretion in deciding that Lands Council’s NFMA claim was unlikely to succeed on the merits.

Next, the Ninth Circuit addressed Lands Council’s claim that USFS was currently out of compliance with the IPNF Forest Plan’s requirement to maintain at least ten percent of old growth trees throughout the forest. USFS relied on two independent monitoring tools, the National Forest Inventory and Analysis program and the IPNF stand-level old growth map, to calculate the percentage of old growth acreage in the IPNF. Each tool found that the IPNF contained approximately twelve percent of old growth. Lands Council presented its own report that concluded that seventy percent of 3000 acres that USFS claimed to be old growth did not meet USFS’s old growth standards, but USFS’s expert disputed the report’s methods, findings, and credibility. The Ninth Circuit reasoned that an “agency must have discretion to rely on the reasonable opinions of its own qualified experts,” when experts advance conflicting views.[46] Thus, the court concluded that USFS did not act arbitrarily and capriciously “in relying on its own data and discounting the alternative evidence offered’ by Lands Council.”[47]

Lands Council also argued that the MBP would violate the IPNF Forest Plan’s requirement to maintain at least ten percent of old growth forest. USFS planned to perform treatments within old growth stands without harvesting old growth trees. Although the court acknowledged that disturbances, other than harvesting, could cause decreases in the old growth percentage, the court held that the MBP does not violate the IPNF Forest Plan’s old growth percentage requirement.[48] Thus, the Ninth Circuit ruled that the district court did not abuse its discretion in concluding that Lands Council was not likely to succeed on the merits of its NFMA claim alleging noncompliance with the IPNF Forest Plan.

Prior to addressing Lands Council’s NEPA claim, the Ninth Circuit discussed the statutory language and purpose of NEPA, as well as its jurisprudence regarding “uncertainties.”[49] The court noted that NEPA and corresponding regulations require agencies undertaking major federal actions to provide “full and fair discussions of significant environmental impacts”[50] but lack any substantive requirement to affirmatively submit every uncertainty in an EIS. The Ninth Circuit acknowledged it had erred when it previously criticized USFS for an EIS’s failure to address a project’s uncertainties “in any meaningful way”[51] but reaffirmed USFS’s duty, under NEPA’s regulations[52] and case law,[53] to “acknowledge and respond to public comments that raise significant scientific uncertainties and reasonably support that such uncertainties exist.”[54] However, USFS does not have to anticipate questions or respond to uncertainties that are “not reasonably supported by any scientific authority.”[55]

The Ninth Circuit held that USFS satisfied NEPA by taking the requisite “hard look” at the environmental impacts of the MBP. Lands Council argued that USFS failed to fully discuss the scientific uncertainty surrounding its strategy for maintaining species viability, referencing two papers that USFS did not discuss. The court reasoned that neither source raised uncertainties about the USFS’s methodology. Rather, those papers supported the USFS’s proposed treatment of old growth habitat. Lands Council also argued that USFS failed to provide adequate evidence that the MBP will improve the habitat of old growth species and failed to adequately evaluate adverse impacts from logging. In response, the Ninth Circuit concluded that the SFEIS described how the MBP would improve tree vigor and resistance to insects and disease and reduce the risk of stand-replacing fires. Additionally, the court noted the USFS’s acknowledgement of potential short-term, negative impacts of treatment, as well as the agency’s position that the MBP would enhance species’ habitat in the long-term, based on the habitat suitability model. In sum, the court ruled that Lands Council is unlikely to succeed on the merits of its NEPA claim.

Having concluded that the district court did not abuse its discretion in finding Lands Council could not show a likelihood of success on the merits, the Ninth Circuit also agreed that the balance of hardships did not tip sharply in Lands Council’s favor, based on a consideration of those affected by an injunction and the public interest.[56] Although the court acknowledged that the balance of harms “usually favors the issuance of an injunction” if an environmental injury is likely,[57] the court declined to adopt a rule that “any potential environmental injury automatically merits an injunction, particularly where . . . the plaintiffs are not likely to succeed on the merits of their claims.”[58] The court balanced the threats to the environment with the economic hardships advanced by the intervenors, noting that even though environmental preservation is in the public’s interest, the MBP benefited the public interest by 1) decreasing the risk of catastrophic fire, insect infestation, and disease, and 2) aiding the struggling local economy and preventing job loss. Because these considerations countered the possible environmental injury alleged by Lands Council, the Ninth Circuit ruled that the district court did not clearly err in concluding that the balance of harms did not tip in Lands Council’s favor.

In summary, the en banc panel of the Ninth Circuit affirmed the district court’s denial of a preliminary injunction. First the court held that NFMA does not require USFS to always verify its methodology with on-the-ground analysis, overruling Ecology Center, Inc. v. Austin. Instead, USFS must simply support conclusions with studies the agency, in its expertise, deems reliable. The court also overruled the suggestion from Idaho Sporting Congress v. Thomas that a habitat could not be used as a proxy for species viability under NFMA; the court instead ruled that USFS can use habitat as a proxy to establish a species’ viability when the disturbance does not reduce suitable habitat in a way that threatens a species’ viability. Furthermore, the Ninth Circuit held that USFS did not fail to conduct a full and fair discussion of environmental impacts under NEPA. Finally, the court concluded that Lands Council failed to show that the balance of hardships tipped sharply in its favor. Based on these conclusions, the Ninth Circuit vacated a three-judge panel’s previous decision that granted Lands Council a preliminary injunction and affirmed the district court.


[1] Boundary County, City of Bonners Ferry, City of Moyie Springs, Everhart Logging, Inc., and Regehr Logging, Inc. intervened on behalf of USFS.

[2] 5 U.S.C §§ 551-559, 701-706, 1305, 3105, 3344, 4301, 5335, 5362, 7521 (2006).

[3] National Forest Management Act of 1976, 16 U.S.C. §§ 472a, 521b, 1600, 1611-1614 (2006) (amending Forest and Rangeland Renewable Resources Planning Act of 1974, Pub. L. No. 93‑378, 88 Stat. 476 (1974)).

[4] National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4370e (2006).

[5] U.S. Dep’t of Agric., U.S. Forest Serv., N. Region, Forest Plan: Idaho Panhandle National Forests (1987), available at http://www.fs.fed.us/ipnf/eco/manage/forestplan.

[6] Lands Council v. McNair (Lands Council III), 494 F.3d 771 (9th Cir. 2008), rev’d en banc, 537 F.3d 981 (9th Cir. 2008).

[7] 430 F.3d 1057 (9th Cir. 2005).

[8] 137 F.3d 1146 (9th Cir. 1998).

[9] Lands Council v. McNair (Lands Council IV), 537 F.3d 981, 1001 (9th Cir. 2008) (en banc).

[10] Id. at 985.The court elaborated that 1) old growth trees need relatively open conditions to sustain growth rates, 2) increased density has caused a decline of forest health because of increased competition for sun and nutrients combined with heightened risk of insects and disease infestations, 3) the resulting “dense, dry forests are at risk for large, stand-replacing fires, due to the build-up of fuels,” and 4) wildlife species that thrive in open forest conditions have suffered. Id.

[11] U.S. Dep’t of Agric., U.S. Forest Serv., Mission Brush Supplemental Final Environmental Impact Statement (2006), available at http://www.fs.fed.us/ ipnf/eco/manage/
nepa/bfnepa/mission_brush/mbsfeis.pdf.

[12] The silvicultural treatments consisted of commercial thinning, both even-aged and uneven-aged regeneration cuts, and sanitation salvage harvesting.

[13] The three timber contracts were 1) the Brushy Mission Sale, 2) the Haller Down Sale, and 3) the Mission Fly By Sale.

[14] Lands Council v. Powell (Lands Council I), 379 F.3d 738 (9th Cir. 2004),amended by 395 F.3d 1019 (9th Cir. 2005).

[15] Lands Council III, 494 F.3d 771 (9th Cir. 2007), rev’d en banc, 537 F.3d 981 (9th Cir. 2008).

[16] Id.

[17] Lands Council IV, 537 F.3d 981, 984 (9th Cir. 2008) (en banc).

[18] The Ninth Circuit noted that a district court abuses its discretion if it “base[s] its decision on an erroneous legal standard or clearly erroneous findings of fact.” Earth Island Inst. v. U.S. Forest Serv., 442 F.3d 1147, 1156 (9th Cir. 2006).

[19] Lands Council v. Martin (Lands Council II), 479 F.3d 636, 639 (9th Cir. 2007)(quoting Clear Channel Outdoor Inc. v. City of Los Angeles, 340 F.3d 810, 813 (9th Cir. 2003)).

[20] Lands Council IV, 537 F.3d at 987(citing 5 U.S.C. § 706(2)(A) (2006)).

[21] Id. at 988.

[22] 430 F.3d 1057 (9th Cir. 2005).

[23] National Forest Management Act of 1976, 16 U.S.C. § 1604(a) (2006).

[24] Id. § 1604(i); see Idaho Sporting Cong., Inc. v. Rittenhouse, 305 F.3d 957, 962 (9th Cir. 2002) (explaining that USFS management activities must comply with the forest plan, which in turn must comply with the Forest Act).

[25] 16 U.S.C. § 1604(g)(3)(B) (2006).

[26] U.S. Dep’t of Agric., supra note 67, at II-28 .

[27] Multiple-Use Sustained-Yield Act of 1960, 16 U.S.C. §§ 528-531 (2006).

[28] Lands Council IV, 537 F.3d 981, 990 (9th Cir. 2008) (en banc)(citing 16 U.S.C. § 1604(e)(1), which lists “outdoor recreation, range, timber, watershed, wildlife and fish, and wilderness” as multiple use considerations).

[29] Id. at 991(citing Ecology Ctr. v. Austin, 430 F.3d 1057, 1065, 1070-71 (9th Cir. 2005)) (internal quotations omitted).

[30] 379 F.3d 738 (9th Cir. 2004), amended by 395 F.3d 1019 (9th Cir. 2005).

[31] Lands Council IV, 537 F.3d at 991. In Lands Council I, USFS had relied on samples from other parts of the forest and aerial photographs, but had not undertaken on-site inspection or verification. Lands Council I, 379 F.3d 738 (9th Cir. 2004), amended by 395 F.3d 1019, 1034-35 (9th Cir. 2005).

[32] Lands Council IV, 537 F.3d at 993.

[33] Forest Guardians v. U.S. Forest Serv., 329 F.3d 1089, 1099 (9th Cir. 2003).

[34] Selkirk Conservation Alliance v. Forsgren, 336 F.3d 944, 954 (9th Cir. 2003)(quoting Marsh v. Or. Natural Res. Council, 490 U.S. 360, 377-78 (1989)).

[35] Lands Council IV, 537 F.3d at 994.

[36] Endangered Species Act of 1973, 16 U.S.C. §§ 1531-1544 (2006).

[37] Lands Council IV, 537 F.3d at 995.

[38] Id.

[39] 88 F.3d 754 (9th Cir. 1996). In Inland Empire, plaintiffs challenged USFS’s analysis of a timber sale’s impact on several sensitive species. Id. at 757.

[40] Id. at 763.Inland Empire also characterized the USFS’s assumption that maintaining threshold proportions of required habitats would ensure a viable population as “eminently reasonable.” Id. at 760-61.

[41] Idaho Sporting Congress, 137 F.3d 1146 (9th Cir. 1998).

[42] Id. at 1154.

[43] Or. Natural Res. Council Fund v. Goodman, 505 F.3d 884, 891 (9th Cir. 2007).

[44] Native Ecosystems Council v. U.S. Forest Serv., 428 F.3d 1233, 1250 (9th Cir. 2005).

[45] Idaho Sporting Cong., Inc. v. Riltenhouse, 305 F.3d 957, 971-72 (9th Cir. 2002).

[46] Lands Council IV, 537 F.3d 981, 1000 (9th Cir. 2008)(quoting Marsh v. Or. Natural Res. Ctr., 490 U.S. 360, 378 (1989)).

[47] Id.(quoting Earth Island Inst. v. U.S. Forest Serv., 351 F.3d 1291, 1302 (9th Cir. 2003)).

[48] This echoed the Ninth Circuit’s conclusion in Lands Council I, 379 F.3d 738 (9th Cir. 2004), amended by 395 F.3d 1019, 1036 (9th Cir. 2005).

[49] Lands Council IV, 537 F.3d at 1001.

[50] 40 C.F.R. § 1502.1 (2007).

[51] Seattle Audobon Soc’y v. Espy, 998 F.2d 699, 704 (9th Cir. 1993); Ecology Center, 430 F.3d 1057, 1065 (9th Cir. 2005).

[52] See 40 C.F.R. §§ 1500.1(b),1502.9(a),1503.4(a), 1502.22 (2007).

[53] Izaak Walton League of Am. v. Marsh, 655 F.2d 346, 377 (D.C. Cir. 1981) (holding that “[s]o long as the environmental impact statement identifies areas of uncertainty, the agency has fulfilled its mission under NEPA”).

[54] Lands Council IV, 537 F.3d at 1001.

[55] Id. at 1002.

[56] The Ninth Circuit concluded the district court applied the correct preliminary injunction standard, requiring 1) a “likelihood of success on the merits and the possibility of irreparable injury,” or 2) “that serious questions going to the merits were raised and the balance of hardships tips sharply in [the plaintiff's] favor.” Lands Council IV, 537 F.3d at 1003(quoting Lands Council II, 479 F.3d 636, 639 (9th Cir. 2007)) (internal citations omitted).

[57] Amoco Prod. Co. v. Vill. Of Gambell, 480 U.S. 531, 545 (1987).

[58] Lands Council IV, 537 F.3d at 1005.

Lands Council v. Martin

Three environmental advocacy groups appealed a decision of the district court granting summary judgment for defendants United States Forest Service and the Forest Supervisor of Umatilla National Forest (collectively Forest Service).[1] The Ninth Circuit reversed the district court on one ground, holding the USFS violated the National Environmental Policy Act (NEPA)[2] by failing to adequately discuss the effects of proposed salvage logging on two roadless areas, but affirmed on two others, holding that the Forest Service complied with the National Forest Management Act (NFMA)[3] in its soil analysis and interpretation of the term “live trees.” The Ninth Circuit remanded the case to the district court.

After an August 2005 forest fire burned approximately 51,000 acres in southeastern Washington, including 28,000 acres in the Umatilla National Forest, the Forest Service began preparations for the School Fire Salvage Recovery Project to harvest dead trees located within the national forest. The Forest Service released its final environmental impact statement (EIS) and record of decision (ROD), choosing to allow salvage logging on 9423 acres. The proposed logging was to be performed on portions of two uninventoried roadless areas, the West Tucannon roadless area (4284 acres) and the Upper Cummins Creek roadless area (966 acres).[4] These two roadless areas are adjacent to the Willow Springs inventoried roadless area, which contains more than 12,000 acres. While a lone road separates West Tucannon and Willow Springs, Upper Cummings Creek and Willow Springs are not separated by a road. The three areas together comprise a contiguous roadless area of more than 13,000 acres.

The Forest Service sought to commence logging immediately to prevent loss of a potential $1,547,000 in timber sales, and the plaintiffs filed suit in the United States District Court for the Eastern District of Washington alleging violations of NEPA and NFMA. Plaintiffs had two principal disputes. The first concerned the Forest Service’s interpretation of the term “live trees” as used in the Umatilla National Forest Land and Resource Management Plan (LRMP). The LRMP prohibited the harvesting of old growth “live trees,” but neither NFMA nor the LRMP defined the term. Plaintiffs contended that dying trees are still alive and logging them would violate the LRMP’s prohibition on harvesting old growth live trees. In an earlier appeal, a panel of the Ninth Circuit agreed and reversed the district court’s decision.[5] Plaintiffs also contended the discussion of the roadless areas in the EIS was inadequate to meet NEPA requirements. The Ninth Circuit affirmed the district court’s decision on this ground, noting the demanding standard of review on appeal from the denial of a preliminary injunction. On remand, the district court issued an injunction prohibiting the cutting of any live tree twenty-one inches or more in diameter at breast height.

As the salvage operation continued, the Forest Service started a new notice and comment process to supplement the EIS with a new definition of “live trees.” The June 11, 2007 supplemental EIS (SEIS) amended the prohibition against harvesting old growth timber by adding a new definition of “live trees” that excluded dying trees, using a predictive method known as the “Scott Mortality Guidelines.”[6] The Forest Service limited the amendment’s geographic and temporal scope by applying it only to the School Fire Salvage Recovery Project. Three months after the issuance of the SEIS, the district court granted summary judgment to the defendants on all claims. Plaintiffs appealed, and the district court issued an injunction pending appeal. The Ninth Circuit reviewed de novo the district court’s grant of summary judgment. On appeal, plaintiffs challenged three aspects of the recovery project: the new definition of live trees, the soil analysis in the EIS, and the discussion of the roadless areas in the EIS.

The Ninth Circuit began its analysis by addressing the amended definition of “live trees” provided by the SEIS. First, plaintiffs alleged the amended definition was arbitrary and capricious because it represented a change in policy that was not adequately explained. The Ninth Circuit rejected this contention, concluding that the amendment was not among the “rare instances” in which the agency’s action is arbitrary and capricious for failure to provide an adequate explanation.[7] The court relied on Morales-Izquierdo v. Gonzales,[8] which held that an unexplained inconsistency is grounds for finding that an interpretation is an arbitrary and capricious change in policy-but only in the rare instances when an agency provides no explanation at all or when the explanation is so unclear or contradictory that there is doubt as to the reason for the change in direction.[9] Here, the Forest Service explained that the policy change was necessary because the plain text definition of “live trees” frustrated its ability to achieve the purpose of the recovery project. Plaintiffs’ disagreement with the merits of the Forest Service’s explanation was insufficient to trigger the “rare instances” exception to the rule stated in Morales-Izquierdo. The Ninth Circuit also declined to consider whether the Forest Service decision was properly supported by science, noting that an agency has discretion to rely on the reasonable opinions of its own qualified experts even if a court finds contrary views more persuasive.[10] This principle also applies to challenges to a specific methodology.[11] The court upheld the Forest Service’s reliance on the newly developed Scott Mortality Guidelines (which were derived from field testing and practical experience but had not yet been published), finding no legal requirement that a methodology be peer reviewed or published in a credible source.[12]

Second, plaintiffs alleged that the Forest Service was bound to use the common meaning of the term “live trees.” The Ninth Circuit disagreed, holding that no statute or precedent suggests that a previously undefined technical term in a forest plan cannot be subsequently clarified. The court noted that “live trees” is not a statutory term and thus is not subject to a Chevron[13] analysis regarding its proper interpretation.

Third, plaintiffs alleged that the Forest Service erred procedurally by concluding that the amendment was not “significant” because it was limited in scope. “Significant” amendments require a lengthy and detailed amendment process; otherwise, a simple notice and comment process is sufficient.[14] The Ninth Circuit rejected plaintiffs’ contention that the amendment was “significant” and thus should have been subjected to greater scrutiny, citing the discretion given to the Forest Service in determining such classifications.[15] Similarly, the Ninth Circuit rejected the argument that the Forest Service arbitrarily enacted a site-specific amendment, applicable to this salvage project, rather than a general amendment that would have applied to the entire forest. The court reiterated the deference given to the Forest Service when it uses its expertise to devise a plan specially suited to a site’s specific characteristics.[16] In this case, “the Forest Service’s decision to limit the scope of the amendment was informed by site-specific characteristics and Forest Service expertise.”[17] Here, the Forest Service chose a definition of “live trees” that assesses the effects of a wildfire on the species of trees found in the affected area. Evidence in the record suggested that the chosen designation may not be appropriate to assess trees affected in other ways, such as prescribed burning, flooding, disease, and insect infestation. As such, the Forest Service “articulated a rational connection between the facts found and the choice made” and did not act arbitrarily.[18]

The Ninth Circuit next analyzed plaintiffs’ challenges to three aspects of the soil analysis in the EIS. First, plaintiffs alleged that the Forest Service did not conduct an on-the-ground soil analysis as required by precedent.[19] The Ninth Circuit disagreed, noting the fifteen-page soil analysis in the EIS that included several references to field verification and observation. On the ROD, plaintiffs could not show that the Forest Service did not actually perform the required on-the-ground soil analysis. Second, plaintiffs alleged that the Forest Service improperly interpreted the term “severe burning” in a provision of the LRMP that required the Forest Service to plan and conduct land management activities so that reductions caused by “severe burning” are minimized. The EIS interprets this provision and others in the Forest Service Handbook as applying only to prescribed burns, not forest fires; the soil analysis therefore did not account for the burning effects of the forest fire. The Ninth Circuit held that the Forest Service’s interpretation was not plainly erroneous or otherwise inconsistent with the language of the LRMP.[20] It is plausible to read the provision as being limited to prescribed burns and not inclusive of naturally occurring effects. Third, the plaintiffs alleged that the Forest Service impermissibly used the “long-term average annual prediction” method rather than the “return period analysis for soil erosion” method. The Ninth Circuit again relied on Inland Empire Public Lands Council v. Schultz,[21] declining to second-guess the methodological choices made by the agency in its area of expertise.[22]

The Ninth Circuit concluded with an examination of plaintiffs’ challenges to the roadless area analysis in the EIS. Plaintiffs alleged that the EIS violated NEPA because it did not contain an adequate discussion of the effects of the proposed logging on the roadless character of two substantial roadless areas. Specifically, the plaintiffs alleged the EIS did not comply with the requirement in Smith v. USFS[23] that roadless areas be discussed in the context of their potential for wilderness designation.[24] In Smith, the court held that “the possibility of future wilderness classification triggers, at the very least, an obligation on the part of the agency to disclose the fact that development will affect a 5,000 acre roadless area.”[25] Specifically, the size of an uninventoried roadless area must be considered in conjunction with the size of any contiguous inventoried roadless area. Here, the Upper Cummings Creek roadless area contains about 1000 acres of uninventoried land and is contiguous to the Willow Springs inventoried roadless area of approximately 12,000 acres. Applying Smith, the Ninth Circuit held that the Upper Cummings Creek-Willow Springs roadless areas are a single “roadless expanse” that, when analyzed together, contain more than 5000 acres.

The Wilderness Act[26] does not limit the potential for wilderness designation to roadless areas 5000 acres or larger, however. An area is suitable for wilderness designation if it contains at least 5000 acres or if it is of sufficient size “as to make practicable its preservation and use in an unimpaired condition.”[27] The West Tucannon roadless area, totaling 4284 acres, falls within this second category. The court thus clarified the rule enunciated in Smith, holding that the Forest Service is required to discuss the effects of proposed logging on roadless areas that are either greater than 5000 acres or of a sufficient size to make the area practicable for preservation under the Wilderness Act. Both roadless areas at issue in this case thus required a discussion of their potential for wilderness designation. The discussion of the roadless areas in the EIS did not meet this requirement because it failed to disclose that Upper Cummings Creek and Willow Springs create a “roadless expanse” larger than 5000 acres or that West Tucannon is of “sufficient size” to trigger the wilderness designation. Thus, the Ninth Circuit reversed the district court’s holding that the discussion in the EIS of the effects of the proposed logging in the roadless areas complied with NEPA requirements.

In conclusion, the Ninth Circuit held that the Forest Service violated NEPA because the agency did not adequately discuss the effects of proposed logging on two roadless areas but that the Forest Service’s soil analysis and interpretation of “live trees” complied with NFMA.


[1] Plaintiffs were The Lands Council, Oregon Wild, Hells Canyon Preservation Council, and Sierra Club. Defendants were the United States Forest Service and the Forest Supervisor of the Umatilla National Forest. American Forest Resource Council, Boise Building Solutions Manufacturing, and Dodge Logging joined the defendants as intervenors.

[2] National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4370e (2006).

[3] National Forest Management Act of 1976, 16 U.S.C. §§ 472a, 521b, 1600, 1611-1614 (2006) (amending Forest and Rangeland Renewable Resources Planning Act of 1974, Pub. L. No. 93-378, 88 Stat. 476 (1974)).

[4] See generally Nat’l Audubon Soc’y v. U.S. Forest Serv., 46 F.3d 1437, 1439-40 (9th Cir. 1993)(describing the history of roadless area designations).

[5] See generally Lands Council v. Martin, 479 F.3d 636 (9th Cir. 2007) (as amended).

[6] In the ROD, the Umatilla National Forest Supervisor explained that “[l]ive trees are defined as trees rated to have a high probability of surviving the effects of fire, and trees rated to have a moderate probability of survival where sampling indicates that at least 50 percent of their basal cambium is alive. Dead trees are defined as trees rated to have a low probability of surviving the effects of fire, and trees rated to have a moderate probability of survival where sampling indicates that more than 50 percent of their basal cambium is dead”, where survival mortality is determined using the Scott Mortality Guidelines. Lands Council v. Martin, 529 F.3d 1219, 1224 (9th Cir. 2008) (quoting the ROD).

[7] Id. at 1225.

[8] 486 F.3d 484 (9th Cir. 2007).

[9] Id. at 493; see also Nat’l Cable & Telecomm. Ass’n v. Brand X Internet Servs., 545 U.S. 967, 981 (2005).

[10] See Marsh v. Or. Natural Res. Council, 490 U.S. 360, 378 (1989); see also Inland Empire Pub. Lands Council v. Schultz (Inland Empire), 992 F.2d 977, 981 (9th Cir. 1993) (“We are in no position to resolve this dispute because we would have to decide that the views of [the plaintiffs'] experts have more merit than those of the Forest Service’s experts.”)

[11] Inland Empire, 992 F.2d at 981 (“We will not second-guess methodological choices made by an agency in its area of expertise.”).

[12] Cf. Baltimore Gas & Elec. Co. v. Natural Res. Def. Council, Inc., 462 U.S. 87, 103 (1983) (holding that “at the frontiers of science . . . a reviewing court must generally be at its most deferential”).

[13] See generally Chevron U.S.A., Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837 (1984).

[14] 16 U.S.C. § 1604(f)(4) (2006);36 C.F.R. § 219.10(f) (2008).

[15] Native Ecosystems Council v. Dombeck, 304 F.3d 886, 900 (9th Cir. 2002) (stating that the “regulations leave to the discretion of the Forest Service the question of whether any given amendment is significant”); see also Prairie Wood Prod. v. Glickman, 971 F. Supp. 457, 463 (D. Or. 1997) (listing four factors from the Forest Service Handbook used to determine if an amendment is significant).

[16] Native Ecosystems Council, 304 F.3d at 900 (holding that Forest Service’s decision to analyze each amendment in a forest plan separately was reasonable).

[17] Lands Council v. Martin, 529 F.3d 1219, 1228 (9th Cir. 2008).

[18] Pac. Coast Fed’n of Fishermen’s Ass’n v. Nat’l Marine Fisheries Serv., 265 F.3d 1028, 1034 (9th Cir. 2001).

[19] See Lands Council v. Powell, 395 F.3d 1019, 1034-35 (9th Cir. 2005) (holding that Forest Service violated NFMA when it relied on a spreadsheet model for soil conditions); Ecology Ctr., Inc. v. Austin, 430 F.3d 1057, 1070-71 (9th Cir. 2005)(applying Powell).

[20] See Forest Guardians v. U.S. Forest Serv., 329 F.3d 1089, 1097 (9th Cir. 2003) (holding that “judicial review of an agency’s interpretation of its own regulations is limited to ensuring that the agency’s interpretation is not plainly erroneous or inconsistent with the regulation”).

[21] 992 F.2d 977 (9th Cir. 1993).

[22] Id. at 981.

[23] 33 F.3d 1072 (9th Cir. 1994).

[24] Id. at 1078-79.

[25] Id. at 1078.

[26] 16 U.S.C. §§ 1131-1136 (2006).

[27] Id. § 1131(c).

Kotrous v. Goss-Jewett Company of Northern California

Plaintiffs-James Kotrous and Adobe Lumber-brought two separate actions to recover costs associated with cleanup of soil and groundwater contamination caused by prior landowners and site users. Plaintiffs incurred the costs voluntarily and sought contribution under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).[1] Relying on the Ninth Circuit’s holding in Pinal Creek Group v. Newmount Mining Corp. (Pinal Creek),[2] which entitled potentially responsible parties (PRPs) to seek contribution under section 107 of CERCLA,[3] the district courts in both actions denied defendants’ motions for dismissal.[4] Defendants filed separate interlocutory appeals.[5] Addressing both appeals in a single opinion, the Ninth Circuit concluded that the United States Supreme Court’s recent decision in United States v. Atlantic Research Corp.[6] overruled the Ninth Circuit’s previous holding in Pinal Creek. Under Atlantic Research, PRPs not subject to a CERCLA section 106 or 107 action who voluntarily incur cleanup costs may seek recovery from other PRPs under section 107 but may not seek contribution under section 113.[7] Consequently, the Ninth Circuit vacated the district court judgments denying the defendants’ dismissal motions and remanded the cases for further proceedings.

Section 107(a) of CERCLA authorizes suits against statutorily defined “responsible parties” to recover costs incurred in cleaning up hazardous waste sites. CERCLA also expressly provides a cause of action for contribution from responsible parties and PRPs under section 113.[8] In Pinal Creek, the Ninth Circuit held that section 113 merely clarified an existing claim for contribution implied by section 107 and that PRPs could only seek contribution, but not cost recovery, from other PRPs under section 107. In 2004, the Supreme Court decided Cooper Industries, Inc. v. Availl Services, Inc. (Cooper Industries),[9] holding that a private party who has not been sued under sections 106 or 107(a) could not sue for contribution under section 113 from other PRPs. Cooper Industries, however, left open the question of whether section 107(a) provides PRPs with a cause of action to recover costs from other PRPs.[10] The Supreme Court later answered that question in the affirmative in Atlantic Research, holding that any private party, including a PRP, who has not been subject to a section 106 or 107 action is entitled to seek cost recovery under section 107.[11] Atlantic Research thus undermined the Ninth Circuit’s holding in Pinal Creek “that an action between PRPs is necessarily for contribution” and prompted the court to reexamine CERCLA jurisprudence in the circuit.[12]

Plaintiffs Koutrous and Adobe Lumber, landowners of sites contaminated by operations of dry cleaning businesses and other PRPs, but who were not themselves the subject of CERCLA suits, brought separate actions under sections 107 and 113 prior to the Supreme Court’s decision in Atlantic Research. Koutrous sought recovery of contribution and costs under section 107(a), and contribution under section 113. The district court rejected defendant’s motion for judgment on the pleadings, concluding that, under Pinal Creek, Koutrous had stated a claim for contribution under CERCLA section 107(a). The district court, however, granted defendant’s motion for interlocutory appeal on the issue of whether Kotrous, as a PRP, could request contribution under section 113 without first being sued under sections 106 or 107(a). Similarly, Adobe Lumber, plaintiff in the second action, sought contribution for costs under sections 107 and 113. The district court, noting that several similar CERCLA cases had reached the Ninth Circuit, denied defendants’ motion to dismiss, but granted defendants’ motion for an interlocutory appeal and stayed discovery proceedings.

On appeal, the Ninth Circuit reviewed the district courts’ statutory interpretations and decisions regarding dismissal and judgment on the pleadings de novo.[13] Noting that the Supreme Court’s holding in Atlantic Research that a PRP may sue for cost recovery under section 107 undermined the holding in Pinal Creek that an action between PRPs is necessarily for contribution, the Ninth Circuit held that Atlantic Research had effectively overruled Pinal Creek. Under Atlantic Research, a PRP that incurs costs voluntarily, without being sued under sections 106 or 107, may bring a suit for recovery of its costs under section 107(a). However, such a PRP must seek recovery under section 107, not contribution under section 113, because section 113 grants an explicit right to contribution only to PRPs with liability stemming from an action under sections 106 and 107(a). Consequently, the court held that Kotrous could seek cost recovery under section 107, but was not entitled to seek contribution under section 113. Similarly, Adobe’s claim for contribution under section 107 could no longer stand under Atlantic Research. The court vacated the orders of the district courts and remanded for proceedings consistent with its holdings, noting that plaintiffs should, on remand, be granted leave to amend their complaints.

In conclusion, the Ninth Circuit consolidated both appeals for review, vacated the district courts’ orders denying defendants’ motions to dismiss, and remanded the cases to the district courts for proceedings consistent with the Ninth Circuit’s holding, based on Atlantic Research, that PRPs that incur costs voluntarily may bring a suit for recovery of its costs under CERCLA section 107(a), but may not seek contribution under section 113.


[1] Comprehensive Environmental Response, Compensation, and Liability Act of 1980, 42 U.S.C. §§ 9601-9675 (2006).

[2] 118 F.3d 1298 (9th Cir. 1997) (holding that section 107 entitles potentially responsible parties (PRPs) to seek only contribution, not cost recovery, from other PRPs).

[3] 42 U.S.C. § 9607 (2006).

[4] The defendants in Kotrous moved for judgment on the pleadings. In Adobe Lumber, the defendants moved to dismiss for failure to state a claim.

[5] The respective district courts granted each defendant’s motion for certification of interlocutory appeal under 28 U.S.C. § 1292(b), and the Ninth Circuit agreed to hear both appeals. The Ninth Circuit then consolidated the two cases for oral argument purposes and addressed them in the same opinion because they presented the same legal issue.

[6] 127 S. Ct. 2331 (2007) (holding that section 107(a) provides PRPs with a cause of action to recover costs from other PRPs, whereas section 113 provides an action for contribution).

[7] Id. at 2339.

[8] 42 U.S.C. § 9613 (2006).

[9] 543 U.S. 157 (2004).

[10] Atlantic Research, 127 S. Ct. at 2334 (2007).

[11] Id.

[12] Kotrous v. Goss-Jewett Co. of N. Cal., 523 F.3d 924, 932 (9th Cir. 2008).

[13] Pinal Creek, 118 F.3d 1298, 1300 (9th Cir. 1997) (standard of review for interpretations of statutes);Ventress v. Japan Airlines, 486 F.3d 1111, 1114 (9th Cir. 2007) (standard of review for grant of judgment on the pleadings); Pakootas v. Teck Cominco Metals, Ltd., 452 F.3d 1066, 1072 (9th Cir. 2006) (standard of review for ruling on a motion to dismiss for a failure to state a claim).

Geertson Seed Farms v. Johanns

Conventional alfalfa growers Geertson Seed Farms and Trask Family Seeds, along with numerous consumer and environmental advocacy organizations (collectively Geertson),[1] brought suit in February 2006 against officials at the United States Department of Agriculture (USDA), the United States Environmental Protection Agency (EPA), and the USDA’s Animal and Plant Health Inspection Service (APHIS) (collectively Defendants), alleging violations of the National Environmental Policy Act of 1969 (NEPA)[2] and other federal statutes. In February 2007, the district court held that APHIS violated NEPA by deregulating genetically engineered alfalfa (Roundup Ready alfalfa) without first preparing an environmental impact statement (EIS) and issued a permanent injunction barring future planting of genetically engineered alfalfa until APHIS’s completion of an EIS.[3] The Ninth Circuit affirmed, holding that the district court correctly issued the permanent injunction and correctly decided not to conduct an evidentiary hearing prior to issuing an injunction.

Monsanto Company (Monsanto) is a large-scale manufacturer of chemical products, including herbicides and pesticides. Monsanto developed lines of Roundup Ready alfalfa, which are resistant to one of the company’s leading herbicides, Roundup. Monsanto licensed the technology to Forage Genetics as the exclusive developer of Roundup Ready alfalfa seed.

APHIS, a division of USDA, is authorized to regulate “the introduction of organisms and products altered or produced through genetic engineering that are plant pests or are believed to be plant pests,” which are also known as “regulated articles.”[4] After APHIS initially classified Roundup Ready alfalfa as a regulated article, Monsanto petitioned APHIS, asking the agency to deregulate the Roundup Ready alfalfa. In response, APHIS published notice in the Federal Register, seeking public comment on the proposed deregulation. The notice explained that APHIS prepared an environmental assessment (EA) in accordance with NEPA that addressed the threat of genetic contamination of conventional alfalfa. Because of the presence of mandatory buffer zones around organic farming operations, the EA concluded it was “unlikely that Roundup Ready alfalfa would have a significant impact on organic farming.”[5]

Of the 663 public comments received in response to the notice, 520 opposed Monsanto’s petition and 137 supported the deregulation of Roundup Ready alfalfa. The alfalfa growers and seed producers who supported the petition argued there was a demand for weed-free alfalfa. Conversely, opponents of the petition expressed concern about inadvertent gene transmission and the possibility that markets might not accept contaminated alfalfa, which farmers could not guarantee to be free from genetic engineering. Opponents further advocated for APHIS to conduct an EIS to analyze the environmental effects of a range of alternatives. In June 2005, APHIS made a finding of no significant impact and unconditionally deregulated Roundup Ready alfalfa.[6]

Fearing that cross-pollination with Roundup Ready alfalfa would cause genetic contamination of conventional alfalfa, Geertson filed suit in federal district court, seeking to enjoin all future planting and harvesting of Roundup Ready alfalfa until APHIS completed an EIS. After conducting a hearing on the parties’ cross-motions for summary judgment, the district court held APHIS “failed to take the required ‘hard look’” demanded by NEPA regarding the extent to which the unconditional deregulation of Roundup Ready alfalfa would lead to genetic contamination of conventional alfalfa.[7] Monsanto and Forage Genetics joined with Defendants at the remedies phase and requested that planting of Roundup Ready alfalfa go forward subject to certain mitigating conditions.

At the remedies stage, the district court held two hearings on the scope of injunctive relief and considered “voluminous evidentiary submissions from both sides.”[8] Geertson sought to enjoin all future planting and harvesting of Roundup Ready alfalfa until the completion of an EIS. Defendants requested that future planting continue, subject to certain conditions proposed by APHIS, such as required isolation from other crops and harvesting methods that minimize gene flow to nongenetically engineered alfalfa seeds. Monsanto and Forage Genetics also requested-and were denied-an evidentiary hearing before the issuance of a permanent injunction. In May 2007, the district court permanently enjoined the planting of all Roundup Ready alfalfa after March 30, 2007, pending APHIS’s completion of an EIS.

On appeal to the Ninth Circuit, Defendants did not challenge the district court’s finding of a NEPA violation. Defendants disputed only the scope of the permanent injunction and whether the district court should have held an evidentiary hearing before issuing the injunction. The Ninth Circuit reviewed the district court’s injunction for abuse of discretion.[9] To obtain a permanent injunction, a plaintiff must show 1) irreparable injury, 2) inadequacy of remedies available at law to compensate for the plaintiff’s injury, 3) the balance of hardships favors issuance of an equitable remedy, and 4) a permanent injunction will serve the public interest.[10]

In challenging the scope of the permanent injunction, Defendants argued the district court erred in its analysis by not applying the four-factor balancing test required by the United States Supreme Court.[11] Defendants argued that the scope of the permanent injunction was overly broad because the district court improperly presumed irreparable injury and did not consider APHIS’s proposed mitigation measures when examining the potential for harm.

The Ninth Circuit rejected Defendants’ argument and held the district court properly applied the traditional balancing test. Although the balance of harms often favors permanent injunctive relief in environmental injury cases,[12] the Ninth Circuit recognized that courts cannot categorically grant or deny injunctive relief in lieu of applying the four-factor test.[13] However, the Ninth Circuit concluded that the district court correctly applied the four-factor test.

First, with regard to irreparable harm requirement, the Ninth Circuit determined the district court did not presume the likelihood of harm based on APHIS’s failure to prepare an EIS. The district court found that Roundup Ready alfalfa already led to genetic contamination of conventional alfalfa crops, despite Monsanto and Forage Genetics’ use of mitigation measures similar to those originally proposed by APHIS. Further, the district court found farmers could not replant alfalfa for two to four years after the removal of contaminated plants. Therefore, the Ninth Circuit held the district court properly concluded that Geerston established the presence of an irreparable injury.

Second, the Ninth Circuit considered the balance of hardships between Geerston and Defendants. The district court recognized the economic harm to Defendants, but noted that Roundup Ready alfalfa accounted for a relatively small percentage of Monsanto’s and Forage Genetics’ total revenues, and that unsold seed could be stored for future planting. By enjoining only future planting and allowing any planted Roundup Ready alfalfa to remain, the Ninth Circuit concluded the district court crafted an injunctive remedy that addressed hardships on both sides. Further, the Ninth Circuit held the district court did not disregard Monsanto and Forage Genetics’ economic losses, but instead concluded that the injury to conventional alfalfa growers and consumers exceeded the harm to Defendants.

Third, in considering the public interest factor, the Ninth Circuit affirmed the district court’s determination that the public interest would benefit from a ban on future planting of Roundup Ready alfalfa until further study of the plant’s impacts. The court reasoned that failure to enjoin further use of the seed could potentially eliminate the availability of conventional and organic alfalfa.

The Ninth Circuit turned next to Defendants’ argument that the district court should have deferred to APHIS’s proposed mitigation measures and permitted future planting of Roundup Ready alfalfa under the agency’s recommended conditions. In rejecting this argument, the Ninth Circuit reasoned that such measures would perpetuate the very system found by the district court to have already caused environmental harm. Accordingly, the Ninth Circuit affirmed the scope of the permanent injunction and held that the district court properly applied the four-factor test for permanent injunctions.

Finally, the Ninth Circuit considered whether the district court erred in denying Monsanto and Forage Genetics’[14] request for an evidentiary hearing. The Ninth Circuit held the district court did not err in declining to hold a further evidentiary hearing because the injunction involved only interim measures. Further, the district court considered other extensive evidence during the remedy phase of the proceedings.

In affirming the lower court’s decision not to hold an evidentiary hearing, the Ninth Circuit relied on the case of Idaho Watersheds Project v. Hahn (Idaho Watersheds).[15] According to the Ninth Circuit, a permanent injunction crafted to ensure compliance with NEPA has a more limited purpose and duration than a typical permanent injunction.[16] Like the permanent injunction in Idaho Watersheds, which the court designed to ensure NEPA compliance, the Ninth Circuit noted that the permanent injunction in the instant case involved interim measures that “would be in place only until the EIS was completed, at which point the parties would have ‘extensive input’ into the determination of which measures would be adopted permanently.”[17] Moreover, the Ninth Circuit recognized that upon APHIS’s completion of the EIS, all parties would have adequate opportunity to address or challenge the permanence of any actions and comment on any new decision regarding deregulation. Finally, relying on Idaho Watersheds, the Ninth Circuit concluded the district court properly denied the request for an evidentiary hearing because the hearing would result in an inquiry similar to the NEPA analysis ordered by the court. Accordingly, the Ninth Circuit affirmed the permanent injunction as a proper application of the traditional balance of harms analysis, holding the district court did not err in declining to hold an evidentiary hearing before issuing the permanent injunction.

In sum, the Ninth Circuit held the district court properly issued an injunction, which would last only until APHIS’s completion of an EIS, and denied the Defendants’ request for an evidentiary hearing.

Judge N. Randy Smith dissented, criticizing the majority’s decision to affirm the district court’s denial of the requisite evidentiary hearing. According to Judge Smith, “the district court was required to conduct an evidentiary hearing before issuing a permanent injunction . . . unless 1) the facts were undisputed; or 2) the adverse party expressly waived its right to an evidentiary hearing.”[18] Finding that the facts were “sharply disputed by the parties,”[19] and that Monsanto and Forage Genetics requested an evidentiary hearing, Judge Smith claimed that the Ninth Circuit improperly denied the request for an evidentiary hearing.

Judge Smith argued that the Ninth Circuit deprived the parties of important procedural rights and created an entirely new exception to the established evidentiary hearing requirement.[20] Judge Smith reasoned that the evidentiary hearing requirement is essential because it affords the district court an opportunity to “better ascertain the nature of the alleged injury and to further understand the balance of the hardships associated with the parties’ varying proposals for injunctive relief.”[21] According to Judge Smith, the consideration of witness testimony, along with the opportunity for cross-examination, is the procedural protection justifying the abuse of discretion standard of review. Because the court did not conduct an evidentiary hearing, Judge Smith argued there was no need for the Ninth Circuit to afford the lower court any discretion in reviewing the court’s permanent injunction order. Finally, reiterating his “serious concerns” with the scope of the injunction, Judge Smith indicated he would have remanded the case and require that the district court conduct an evidentiary hearing.[22]


[1] The consumer and environmental advocacy organizations included the Center for Food Safety, Beyond Pesticides, Cornucopia Institute, Dakota Resource Council, National Family Farm Coalition, Sierra Club, and Western Organization of Resource Councils.

[2] Comprehensive Environmental Response, Compensation, and Liability Act of 1980, 42 U.S.C. §§ 4321-4370e (2006).

[3] Geertson Farms, Inc. v. Johanns, No. C 06-01075 CRB, 2007 WL 1302981 (N.D. Cal. 2007).

[4] See 7 C.F.R. § 340.0(a)(2) n.1 (2008).

[5] Geertson Seed Farms v. Johanns, 541 F.3d 938, 942 (9th Cir. 2008).

[6] See Monsanto Co. and Forage Genetics International; Availability Determination of Nonregulated Status for Alfalfa Genetically Engineered for Tolerance to the Herbicide Glyphosate, 70 Fed. Reg. 36,917, 36,918 (June 27, 2005).

[7] Geertson Seed Farms, 541 F.3d at 942.

[8] Id. at 943.

[9] See Idaho Watersheds Project v. Hahn, 307 F.3d 815, 823 (9th Cir. 2002) (reviewing for an abuse of discretion when there area no issues of law).

[10] N. Cheyenne Tribe v. Norton, 503 F.3d 836, 943 (9th Cir. 2007)(citing eBay v. MercExchange, L.L.C., 547 U.S. 388, 391 (2006)).

[11] See eBay v. MercExchange, L.L.C., 547 U.S. 388, 394 (2006).

[12] See Amoco Prod. Co. v. Vill. of Gambell, 480 U.S. 531, 545 (1987).

[13] See eBay, 547 U.S. at 394.

[14] APHIS did not request an evidentiary hearing and did not join with Monsanto and Forage Genetics in challenging this issue on appeal.

[15] 307 F.3d 815, 831 (9th Cir. 2002) (holding that an evidentiary hearing was not required before issuing permanent injunction in a case involving violation of NEPA).

[16] Id.

[17] Geerston Seed Farms, 541 F.3d 938, 947 (9th Cir. 2008)(quoting Idaho Watersheds, 307 F.3d at 831).

[18] Id. at 948 (Smith, J., dissenting).

[19] Id.

[20] See Charlton v. Estate of Charlton, 841 F.2d 988, 989 (9th Cir. 1988).

[21] Geerston Seed Farms, 541 F.3d at 949 (Smith, J., dissenting).

[22] Id.

Friends of Yosemite Valley v. Kempthorne

Friends of Yosemite Valley and Mariposans for Environmentally Responsible Growth (collectively Friends) sued the National Park Service (NPS) in the United States District Court for the Eastern District of California, alleging NPS management of the Merced River violated the Wild and Scenic Rivers Act (WSRA),[1] the National Environmental Policy Act (NEPA),[2] the Administrative Procedure Act (APA),[3] and previous Ninth Circuit decisions concerning management of the river.[4] The Ninth Circuit affirmed the district court’s order granting partial summary judgment in favor of the plaintiffs. The Ninth Circuit held that the 2005 Revised Comprehensive Management Plan (RCMP) violated the WSRA and previous court rulings because it was not a single, comprehensive document and because it failed to describe an actual level of visitor use that would not adversely impact the Merced River. The court also held that the supplemental environmental impact statement (SEIS) violated NEPA because it lacked a no-action alternative and because its range of action alternatives was unreasonably narrow. The court remanded the case for action consistent with its opinion.[5]

Congress designated sections of the Merced River for inclusion in the Wild Scenic River System in 1987, including parts flowing through Yosemite National Park and its administrative site, El Portal.[6] Congress enacted the WRSA in 1968 “out of concern for the preservation of United States rivers, many of which had been subjected to overdevelopment and damming.”[7] The WSRA framework uses specific “outstandingly remarkable values” (ORVs) to justify initial designations of rivers[8] and also provides standards for evaluating the compatibility of proposed projects with the protection and enhancement of the ORVs of designated rivers.[9] Following designation, administering agencies must establish river boundaries and classify the river or its segments within one year and prepare a comprehensive management plan (CMP) that addresses “resource protection, development of lands and facilities, user capacities, and other management practices necessary or desirable to achieve the [WSRA's] purposes” within three years.[10] In pursuit of interdepartmental consistency, the Agriculture and Interior departments issued joint WSRA interpretative guidelines in 1982. The Final Revised Guidelines for Eligibility, Classification and Management of River Areas (Secretarial Guidelines) require the CMP to contemplate the kinds and amount of public use, including recreation, that each river can sustain without adverse affect on its ORVs.[11]

NPS was statutorily required to prepare and adopt a valid CMP within three years of the Merced’s wild and scenic designation in 1987, but the agency failed to meet this deadline and litigation ensued. After being ordered by the district court to issue a CMP for the Merced,[12] NPS complied in 2000, more than twelve years after the CMP was due. In 2003, the Ninth Circuit held the 2000 CMP failed to adequately address user capacities and improperly drew the boundaries of the Merced River at El Portal.[13] After clarifying its 2003 decision, the Ninth Circuit remanded the case to the district court, granted a temporary stay of proceedings, and enjoined NPS from implementing projects developed in reliance on the invalid CMP.[14] On remand, the district court ordered NPS to complete a new or revised CMP and an SEIS.[15]

After public scoping and review, NPS issued its 2005 revised plan (RCMP), which Friends challenged under the WRSA, NEPA, the APA, and as violating the Ninth Circuit’s earlier opinions. The Ninth Circuit reviewed NPS’s appeal from the district court’s grant of plaintiff’s motion for summary judgment de novo.[16] Thus, the court reviewed NPS’s action under the APA, allowing the court to set aside agency decisions that are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law.”[17] More specifically, the Ninth Circuit required NPS to demonstrate a “rational connection” between the data described and decisions made.[18] Applying this standard of review, the Ninth Circuit affirmed the district court’s holdings regarding the RCMP’s deficiencies in addressing user capacities and serving as a single, comprehensive plan, as well as the failure of the SEIS to provide a “no action” alternative and a reasonable range of action alternatives.

The Ninth Circuit had previously instructed NPS to adopt specific limits on user capacity that “describe an actual level of visitor use that will not adversely impact the Merced’s ORVs.”[19] In response to this order, the RCMP revised the 2000 Visitor Experience and Resource Protection (VERP) program to address this instruction. On appeal, NPS argued that the RCMP promulgated measurable limits on user capacities in 1) the Wilderness Trailhead Quota System and Superintendent’s Compendium limits, 2) the VERP indicators and standards, and 3) the User Capacity Management Program’s interim limits. The Ninth Circuit first dismissed NPS’s reliance on the Wilderness Trailhead Quota System limits on overnight users in the wilderness area and the Superintendent’s Compendium limits on time and location of specific activities because both methods predated the RCMP. Then, the court addressed NPS’s remaining arguments in greater detail.

The Ninth Circuit affirmed the district court’s finding that VERP failed to address user capacities, holding that it was reactive and not oriented toward preventing degradation. The VERP program’s description of indicators and standards to monitor and maintain was reactive because it did not “describe an actual level of visitor use that will not adversely impact the Merced’s ORVs.”[20] NPS argued that the VERP monitoring triggers could spur action prior to degradation. However, the Ninth Circuit criticized the permissive language of the RCMP regarding management action and stated that VERP standards must trigger management before degradation occurs, instead of allowing action when conditions approach the standard.

The Ninth Circuit also affirmed the district court’s conclusion that the RCMP’s interim limits restricting the kinds and amounts of visitor use for five years during VERP program testing failed to “describe an actual level of visitor use that will not adversely affect” the Merced River.[21] The court rejected NPS’s argument that holding facility levels to 1987 levels was reasonable, noting that such an argument lacked authority. Under WSRA’s “protect and enhance” command,[22] the court reasoned NPS had a responsibility to address past degradation, including the degradation that existed in 1987, as well as ongoing degradation. The court concluded that the multitude of recreational facilities and services at the Merced failed to be “river-related or river dependant” and “rare, unique, or exemplary in a regional or national context,” both of which were required elements of establishing recreation as an ORV.[23] The Ninth Circuit also reasoned that the interim limits violated the statutory command of WSRA by failing to demonstrate a “primary emphasis” on the protection of the Merced.[24] Finally, the court concluded that the origin of the interim limits in the current capacity limits lacked a rational connection with facts found.[25]

Next, the Ninth Circuit affirmed the district court’s finding that NPS failed to produce a single, comprehensive plan that covered all required elements, including the “kinds and amounts of public use which the river area can sustain.”[26] The Ninth Circuit affirmed the district court’s rejection of a December 2005 “Presentation Plan” that integrated the CMP and RCMP because it lacked public review and contradicted the RCMP’s status as the final revised plan. In stressing its single-plan requirement, the court rejected the issuance of the RCMP as a supplemental volume that cross-referenced the original CMP. Substantively, the court held the RCMP was not comprehensive because, although it addressed the “amounts” of use, it failed to also address the “kinds” of permissible use. Finally, the Ninth Circuit rejected NPS’s argument that both the district court and appellate court unlawfully assumed responsibility for revising the 2000 CMP.[27] Instead, the Ninth Circuit concluded that each court properly entered a judgment on the issues and remanded the revisions to NPS for reconsideration.

Finally, the Ninth Circuit affirmed the district court’s holding that NPS violated NEPA because the SEIS was invalid for lacking a no-action alternative and a reasonable range of action alternatives. The no-action alternative proposed managing the Merced River corridor under the CMP. Thus, the alternative referenced a “status quo” management that had already been rejected,[28] and the only basis for the no-action alternative rested in the RCMP’s incorporation of the CMP’s elements. The Ninth Circuit reasoned that approving a baseline alternative on the assumption of a proposed plan’s validity was “logically untenable.”[29]

The Ninth Circuit used the “rule of reason” standard in affirming the district court’s determination that the SEIS lacked a reasonable range of action alternatives. Each of the three action alternatives in the SEIS was based on the VERP program, which failed to adequately address user capacity, even though NPS, from its meeting notes, acknowledged the need for reasonable range of user capacity alternatives. Additionally, the Ninth Circuit reasoned that because each action alternative proposed five-year interim limits consistent with current use, the alternatives were essentially identical. Even though two alternatives included maximum use levels and annual visitation limits, the court held the SEIS violated NEPA because the similar alternatives were not sufficiently varied to provide for a genuine, informed choice.

In conclusion, the Ninth Circuit held that the RCMP violated WSRA and Ninth Circuit precedent because it was not a single, comprehensive document that described the actual level of use that would not adversely impact the Merced River. Furthermore, the court held that the agency’s SEIS violated NEPA because it lacked a genuine no-action alternative and its range of action alternatives were indistinguishable. The court remanded the case to the district court for proceedings consistent with its opinion.


[1] 16 U.S.C. §§ 1271-1287 (2006).

[2] National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321-4370e (2006).

[3] 5 U.S.C. §§ 551-559, 701-706, 1305, 3105, 3344, 4301, 5335, 5362, 7521 (2006).

[4] The Ninth Circuit reviewed a previous comprehensive management plan for the Merced River in 2003, Friends of Yosemite Valley v. Norton (Yosemite I), 348 F.3d 789 (9th Cir. 2003),and clarified the opinion in 2004 in Friends of Yosemite Valley v. Norton (Yosemite II), 366 F.3d 731 (9th Cir. 2004).

[5] The Ninth Circuit dismissed NPS’s interlocutory appeal from the district court’s order enjoining nine projects in the Merced River Corridor because the agency failed to address the injunction issue in its appellate briefs, and thus its arguments were deemed waived. E.g., Smith v. Marsh, 194 F.3d 1045, 1052 (9th Cir. 1999); Miller v. Fairchild Indus. Inc., 797 F.2d 727, 738 (9th Cir. 1986).

[6] See Pub. L. No. 100-149, 101 Stat. 879 (Nov. 2, 1987) (codified at 16 U.S.C. § 1274(a)(62)(A) (2006)).

[7] Friends of Yosemite Valley v. Kempthorne (Yosemite III), 520 F.3d 1024, 1027 (9th Cir. 2008).

[8] Wild and Scenic Rivers Act, 16 U.S.C. § 1271 (2006).

[9] Id. § 1281(a).

[10] Id. § 1274(d)(1).

[11] Final Revised Guidelines for Eligibility, Classification and Management of River Areas, 47 Fed. Reg. 39,454, 39,458-59 (Sept. 7, 1982) [hereinafter Secretarial Guidelines].

[12] Sierra Club v. Babbitt, 69 F. Supp. 2d 1202, 1263 (E.D. Cal. 1999).

[13] Yosemite II, 366 F.3d 731 (9th Cir. 2004)(clarifying 2003 Yosemite I decision).

[14] Id.

[15] Id.The district court also enjoined certain projects until completion of the new or revised CMP.

[16] Alaska Ctr. for the Env’t v. U.S. Forest Serv., 189 F.3d 851, 857 (9th Cir. 1999) (citation omitted).

[17] Yosemite III, 520 F.3d 1024, 1032 (9th Cir. 2008)(quoting Yosemite I, 348 F.3d 731, 793 (9th Cir. 2003)).

[18] Id.(quoting Pub. Citizen v. Dep’t of Transp., 316 F.3d 1002, 1020 (9th Cir. 2003)). With regard to environmental impact statements (EISs), the Ninth Circuit applied a “rule of reason” standard that evaluates whether an EIS “contains a reasonably thorough discussion of the significant aspects of the environmental consequences.” Yosemite I, 348 F.3d 789, 800 (9th Cir. 2003).The court equated this standard with the “abuse of discretion” standard. Id.

[19] Yosemite I, 348 F.3d at 797.This is the Ninth Circuit’s interpretation of 16 U.S.C. § 1281(a)and the Secretarial Guidelines, supra note 561, at 39, 458-59.

[20] Yosemite III, 520 F.3d at 1034(quoting standard set forth in Yosemite I, 348 F.3d at 797).

[21] Id.

[22] Wild and Scenic Rivers Act, 16 U.S.C. § 1281(a) (2006).

[23] Yosemite III, 520 F.3d at 1035 n.5.

[24] See id. § 1281(a) (requiring that administration of rivers designated under WSRA place “primary emphasis” on a river’s “esthetic, scenic, historic, archeologic, and scientific features”).

[25] The Ninth Circuit’s earlier decision in High Sierra Hikers Ass’n v. Blackwell, 390 F.3d 630 (9th Cir. 2004),emphasized some of the problems with maintaining use at existing levels. In that case, the court concluded continuance of existing use levels at best “failed to balance the impact that that level of commercial activity was having on the wilderness character of the land” and at worst “elected recreational activity over the long-term preservation of the wilderness character of the land.” Id. at 647.

[26] Final Revised Guidelines for Eligibility, Classification and Management of River Areas, 47 Fed. Reg. 39,454, 39,458-59 (Sept. 7, 1982).

[27] In support of its argument, NPS cited Federal Power Commission v. Idaho Power Co., 344 U.S. 17 (1952), which explains “the function of the reviewing court ends when an error of law is laid bare. At that point the matter once more goes to the [agency] for reconsideration.” Id. at 20.

[28] Yosemite II, 366 F.3d 731, 731 (9th Cir. 2004).

[29] Yosemite III, 520 F.3d 1024, 1038 (9th Cir. 2008).

Fall River Rural Electric Cooperative v. Federal Energy Regulatory Commission

Fall River Rural Electric Cooperative (Fall River) petitioned the Ninth Circuit for review of two orders issued by the Federal Energy Regulatory Commission (FERC) in response to Fall River’s license application to construct and operate a new hydroelectric power facility on the Madison River in Montana. In denying Fall River’s application and request to hold the proceedings in abeyance, as well as Fall River’s request for a rehearing, FERC concluded the proposed project was barred by section 6 of the Federal Power Act (FPA).[1] The Ninth Circuit denied Fall River’s petition for review, finding substantial evidence in support of FERC’s factual determination under the FPA, and concluding FERC’s orders were consistent with the agency’s precedent and regulations.

Hebgen Dam, a water storage and release facility, is one of nine developments that comprise the Missouri-Madison Hydroelectric Project on a 324-mile stretch of river in southwest Montana. The project is licensed by FERC to Pennsylvania Power & Light Montana (PPL). In 2001, FERC granted Fall River a preliminary permit to determine the feasibility of constructing and operating a hydroelectric facility at Hebgen Dam. PPL did not object to the preliminary permit and entered into negotiations with Fall River regarding a possible site use and operations agreement. Fall River submitted its final license application for the proposed Hebgen Dam project in May 2004. The application proposed several changes and additions to the existing Hebgen Dam, which included the construction of a new powerhouse and several modifications to the existing structure of the dam.[2] Fall River estimated that construction would take approximately three months.

Under section 6 of the FPA, FERC cannot substantially alter existing, licensed projects without the consent of the licensee.[3] In light of section 6 of the FPA, FERC initially agreed to continue processing Fall River’s final license application based on the understanding that Fall River and PPL were actively negotiating an agreement for the construction and operation of the proposed facility. After PPL terminated all negotiations with Fall River, however, FERC dismissed Fall River’s license application. Upon review, FERC concluded section 6 of the FPA barred the proposal because the project would substantially alter PPL’s licensed project, and Fall River did not obtain the requisite consent from licensee PPL. FERC also denied Fall River’s request to hold the application in abeyance because PPL expressed no intent to resume negotiations with Fall River. Subsequently, a three-person panel of FERC commissioners denied Fall River’s request for rehearing, concluding the project required substantial physical alterations and would create potential operating problems related to the joint-use of the Hebgen Dam site.

In its petition for review, Fall River argued that 1) FERC’s orders denying its license application and request to hold the proceedings in abeyance were not supported by substantial evidence, 2) FERC’s decision was inconsistent with the agency’s precedent, regulations, and issuance of a preliminary permit, and 3) FERC failed to consider whether PPL impliedly consented to the project. The Ninth Circuit reviewed FERC’s decision under the Administrative Procedure Act (APA)[4] to determine whether FERC’s action was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.[5] When FERC’s findings are supported by substantial evidence, the Ninth Circuit accepts FERC’s factual findings as conclusive.[6]

Reviewing Fall River’s petition, the Ninth Circuit first rejected Fall River’s contention that its proposal would not materially alter PPL’s existing project works, operations, or power generation. The court noted that an “alteration” under section 6 of the FPA is a factual issue determined on a case-by-case basis,[7] but Fall River and FERC agreed that to violate the FPA, a “proposed project must substantially alter an existing license.”[8] FERC concluded that Fall River’s project involved substantial physical alterations to the existing facility, including installation of new gates on the intake tower, excavation of a large area of the dam, reconfiguration of the outlet conduit, and installation of a valve house and new penstock. FERC also determined the “potential for ‘joint-use operational problems [between PPL and Fall River] would be a substantial alteration of the existing license.’”[9] The Ninth Circuit explained that such actions “fundamentally change the physical characteristics and operation of the Hebgen Development,” and that “Fall River apparently [did] not appreciate the cumulative impact of its proposed project.”[10] Accordingly, the Ninth Circuit concluded that FERC’s factual findings regarding the physical alterations and operational interference were supported by substantial evidence.

The court next considered whether FERC’s decision on Fall River’s application was consistent with the agency’s prior precedent. First, the Ninth Circuit examined FERC’s analysis of three cases where the agency found the applicant proposed a substantial alteration to existing licenses.[11] In Niagara Mohawk Power Corporation,[12] FERC rejected a license application to modify an existing development because the project required significant construction and alterations of the existing licensed project, which would effectively lead to the closure of the original facility.[13] The Ninth Circuit reasoned that Fall River’s proposal likewise required “more than an insubstantial amount of construction.”[14] In a second case, FERC denied an application that proposed modifying an existing dam and powerhouse because it involved significant structural modifications to the project dam and project works adjacent to the dam.[15] Although Fall River did not ask to modify an existing powerhouse, the Ninth Circuit determined Fall River hoped to construct a new powerhouse and make other alterations to the Dam. Finally, FERC considered the case of Green Island Power Authority (Green Island),[16] in which a proposal to construct a new dam was denied because it would render an existing project inoperable.[17] In examining Green Island, the Ninth Circuit concluded FERC only used Green Island as an “extreme example of a substantial alteration” and did not imply that Fall River’s proposal needed to be as extreme as the Green Island proposal to amount to a substantial alteration.[18]

The Ninth Circuit also reviewed FERC’s evaluation of earlier decisions where the agency found no substantial alteration to existing licenses. In Water Basin Water Conservancy District,[19] FERC found no substantial alteration to a license to construct a penstock under an existing canal because construction was only expected to take three to seven days and would result in no physical interference to prior licensees once finished.[20] In contrast, the Ninth Circuit determined Fall River’s construction project was expected to take eight months and would “fundamentally alter the flow of water through Hebgen Dam.”[21] Additionally, in Howard W. Bair,[22] FERC granted a preliminary permit that proposed extending an existing pipe by forty feet.[23] The Ninth Circuit distinguished Bair, concluding Bair involved only a preliminary permit and small-scale changes, whereas Fall River’s proposals were “far more extensive.”[24] Finally, in two prior cases, FERC concluded that a 0.3% reduction in power generation did not constitute a substantial alteration.[25] Fall River argued that similarly, its proposed project would not reduce power generation at Hebgen Dam. However, the Ninth Circuit noted that while power generation would not be reduced at Hebgen Dam,[26] the two earlier cases were distinguishable because they lacked “physical modifications comparable to those now proposed by Fall River.”[27] Reviewing the two lines of prior precedent, the Ninth Circuit concluded FERC’s orders regarding Fall River were consistent with the agency’s past decisions and therefore entitled to deference.

The court next considered Fall River’s assertion that FERC’s orders were inconsistent with its regulations and the agency’s issuance of a preliminary permit. Fall River argued that because its final license application was substantially identical to the preliminary application granted by FERC, FERC’s denial of its final license application constituted a change in policy that required a reasoned explanation.[28] The Ninth Circuit noted that FERC’s practice is to issue preliminary permits unless there is a clear indication that a project would involve impermissible alterations to an existing license, [29] or there is a “permanent legal barrier” to the proposed project.[30] Further, FERC’s issuance of a preliminary permit does not indicate the agency made a decision on the merits of a license application.[31] In rejecting Fall River’s argument, the Ninth Circuit concluded FERC’s orders were consistent with its regulations because it was not clear at the time of the preliminary permit application that Fall River’s project would substantially alter PPL’s license, nor was there any indication that a permanent legal barrier would preclude issuance of the final permit.

Lastly, the Ninth Circuit rejected Fall River’s argument that FERC failed to consider whether PPL impliedly consented to the project. The court found no basis to require FERC to thoroughly analyze each and every argument in its decision-making process, particularly in Fall River’s case because section 6 of the FPA “unequivocally” states that FERC may only alter a license if the licensee consents to the change. Further, Fall River did not cite any cases showing there could be an implied agreement by the licensee to the permit changes. Finally, the court deemed the consent argument waived because Fall River did not specifically argue the issue in its opening brief.

In sum, the Ninth Circuit denied Fall River’s petition for review. The court concluded that substantial evidence supported FERC’s determination that the proposal would substantially alter PPL’s license, that FERC’s orders were consistent with the agency’s precedent and issuance of a preliminary permit, and that PPL did not impliedly consent to Fall River’s proposal.


[1] 16 U.S.C. § 799 (2006).

[2] Fall River’s proposed modifications to the Hebgen Development included 1) constructing a powerhouse with a single turbine generator unit downstream from the dam, 2) strengthening the conduit to withstand the full reservoir pressure for power generation through pressure grouting and steel lining, 3) bifurcating the conduit, 4) installing a steel penstock to direct the water flow to the new powerhouse, 5) erecting a new power transmission line, and 6) modifying the dam to use all four-instead of only two-of the existing intake tower openings. Fall River Rural Elec. Coop. v. FERC, 543 F.3d 519, 522-23 (9th Cir. 2008).

[3] Section 6 of the FPA states that “[l]icenses . . . may be altered . . . only upon mutual agreement between the licensee and the Commission,” thus requiring that the licensee, in this case PPL, consent to any proposed alterations. 16 U.S.C. § 799 (2006).

[4] 5 U.S.C. §§ 551-559, 701-706, 1305, 3105, 3344, 4301, 5335, 5362, 7521 (2006).

[5] See id. § 706(2);Cal. Dep’t of Water Res. v. FERC, 489 F.3d 1029, 1035 (9th Cir. 2007).

[6] See 16 U.S.C. § 825l(b) (2006); Bear Lake Watch, Inc. v. FERC, 324 F.3d 1071, 1076 (9th Cir. 2003).

[7] Universal Elec. Power Co., 92 F.E.R.C. ¶ 61,242, 61,768 (2000).

[8] Fall River Rural Elec. Coop. v. FERC, 543 F.3d 519, 525 (9th Cir. 2008) (emphasis added).

[9] Id. at 527.

[10] Id.

[11] Id. at 529.

[12] 29 F.E.R.C. ¶ 61,005 (1984).

[13] Id. ¶ 61,010.

[14] Fall River Rural Elec. Coop., 543 F.3d at 528.

[15] JDJ Energy Co., 41 F.E.R.C. ¶ 61,354 (1987).

[16] 110 F.E.R.C. ¶ 61,034 (2005).

[17] Id. ¶ 61,108.

[18] Fall River Rural Elec. Coop., 543 F.3d at 528.

[19] 50 F.E.R.C. ¶ 61,409 (1990).

[20] Id. ¶ 62,263.

[21] Fall River Rural Elec. Coop., 543 F.3d at 529.

[22] 20 F.E.R.C. ¶ 61,092, (1982).

[23] Id. 61,194.

[24] Fall River Rural Elec. Coop., 543 F.3d at 529.

[25] See Pac. Gas & Elec. Co. v. FERC, 720 F.2d 78, 89 (D.C. Cir. 1983); Fluid Energy Systems, Inc., 24 F.E.R.C. ¶ 61,298, 61,615 (1983).

[26] Hebgen Dam lacked existing power generating facilities, so the addition of a new power generating facility could only increase the amount of power generated at the dam.

[27] Fall River Rural Elec. Coop., 543 F.3d at 529.

[28] See Flagstaff Med. Ctr., Inc. v. Sullivan, 962 F.2d 879, 886 (9th Cir. 1992) (noting that “changes in agency interpretation must be supported by a ‘reasoned analysis’”).

[29] See Kamargo Corp., 53 F.E.R.C. ¶ 61,411, 62,439 (1990).

[30] Town of Summersville v. FERC, 780 F.2d 1034, 1038-39 (D.C. Cir. 1986).

[31] Id.